Providing and fixing 150 mm bright finished floor brass door stopper with rubber cushion, necessary brass screws etc. to suit shutter thickness complete

Item number
14.34
Analysis basis
10 nos
Priced inputs
5
Derived rate
₹271.45/ NOS
D-01/RATE ANALYSISITEM 14.34

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.34 (Providing and fixing 150 mm bright finished floor brass door stopper with rubber cushion, necessary brass screws etc. to suit shutter thickness complete) is derived from 5 priced inputs for 10 nos and works out to ₹271.45 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 14.34DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0417MATBrass 150 mm floor door stopper (0.357kg)Brass 150 mm floor door stopper weighing not less than 0.357kgeach10175.001,750.00
0450MATBrass screws 40 mm100 Nos0.4187.0074.80
9977MATCarriage of materialL.S.2.732.276.20
0111LABCarpenter 1st classday0.07897.0062.79
9999MATSundries (wooden plugs including fixing in the floor)L.S.6.372.2714.46
BUILD-UP TO RATE
TOTAL
1,908.25
Add 1 % Water charges on “W”
+19.08
TOTAL
1,927.33
Add GST on “X” (multiplying factor 0.2127)
+409.94
TOTAL
2,337.27
Add 15% CPOH on “Y”
+350.59
TOTAL
2,687.86
Add Cess @ 1% on “Z”
+26.88
Cost of 10 Nos
2,714.74
Cost of each
271.47
SAY
₹271.45
D-02/SOURCEPRINTED PAGE 1073
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1073

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1073. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.