Providing and fixing bright finished brass flush bolts with necessary brass screws etc. complete

250 mm
Item number
14.33.1
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹285.05/ NOS
D-01/RATE ANALYSISITEM 14.33.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.33.1 (Providing and fixing bright finished brass flush bolts with necessary brass screws etc. complete : 250 mm) is derived from 4 priced inputs for 10 nos and works out to ₹285.05 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 14.33.1DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0404MATBrass flush bolt 250 mmeach10175.001,750.00
0452MATBrass screws 25 mm100 Nos0.6110.0066.00
9977MATCarriage of materialsL.S.3.642.278.26
0111LABCarpenter 1st classDay0.2897.00179.40
BUILD-UP TO RATE
TOTAL
2,003.66
Add 1 % Water charges on “W”
+20.04
TOTAL
2,023.70
Add GST on “X” (multiplying factor 0.2127)
+430.44
TOTAL
2,454.14
Add 15% CPOH on “Y”
+368.12
TOTAL
2,822.26
Add Cess @ 1% on “Z”
+28.22
Cost of 10 hinges
2,850.48
Cost of each
285.05
SAY
₹285.05
D-02/SOURCEPRINTED PAGE 1072
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1072

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1072. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.