CPWD Analysis of Rates · Reinforced Cement Concrete

Providing and laying Reinforced cement concrete for construction of piers, abutments, portal frames, pier caps and bearing pedestals and seismic arresters over pier/ abutment caps at all locations with specified grade using Ordinary Portland Cement (conforming to strength requirement of IS:8112) including the cost of steel centering and shuttering etc. complete, including testing of materials etc. for casting pier & pier cap in one/two stage, necessary tools, plants, machinery and all related operations as required to complete the work as per drawings and Specifications with all leads, lifts and depths true to level and position but excluding the cost of providing reinforcement. Reinforcement shall be measured and paid separately. Note:- Cement content considered in this item is 480 Kg./ Cum. Excess/ less cement used as per design mix is payable/ recoverable separately

Reinforced Cement Concrete -M-60

Item number
5.48.2
Analysis basis
Detail of cost for 120 cum.
Priced inputs
1
Derived rate
9,500.30 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.48.2 Providing and laying Reinforced cement concrete for construction of piers, abutments, portal frames, pier caps and bearing pedestals and seismic arresters over pier/ abutment caps at all locations with specified grade using Ordinary Portland Cement (conforming to strength requirement of IS:8112) including the cost of steel centering and shuttering etc. complete, including testing of materials etc. for casting pier & pier cap in one/two stage, necessary tools, plants, machinery and all related operations as required to complete the work as per drawings and Specifications with all leads, lifts and depths true to level and position but excluding the cost of providing reinforcement. Reinforcement shall be measured and paid separately. Note:- Cement content considered in this item is 480 Kg./ Cum. Excess/ less cement used as per design mix is payable/ recoverable separately Reinforced Cement Concrete -M-60 — is derived from 1 priced inputs for 120 cum and works out to ₹9,500.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Providing M 60 grade reinforced Cement
  • Concrete data (lot) for 120.00 cum
  • and machinery excluding formwork to cater
  • Add 1.4 per cent of cost of material, Labour
CodeInputUnitQuantityRate (INR)Amount (INR)
Sub Analysis no 5.48Y (Annexure) for item 5.48.2Rate as per item 5.48YSub-analysiseach17,12,947.657,12,947.65
Add 11 per cent of cost of material, labour and machinery for formwork on P
78,424.24
for extra lift on P
9,981.27
TOTAL
8,01,353.16
Add 1 % Water charges on “W”
8,013.53
TOTAL
8,09,366.69
Add GST on “X” (multiplying factor 0.2127)
1,72,152.29
TOTAL
9,81,518.98
Add 15% CPOH on “Y”
1,47,227.85
TOTAL
11,28,746.83
Add Cess @ 1% on “Z”
11,287.47
Cost of 120 cum
11,40,034.30
Cost of 1 cum
9,500.29
Say
9,500.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 297. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works