Providing and fixing of expansion joint system related with wall joint (internal/external) location as per drawings and direction of Engineer-InCharge. The joints shall be of extruded aluminum base members, self aligning / centering arrangement and support plates as per ASTM B22102. The material shall be such that it provides an Expansion Joints System suitable for vertical wall to wall/ wall to corner application, both new and existing construction in office Buildings & complexes with no slipping down tendency amongst the components of the Joint System. The Joint System shall utilize light weight aluminum profiles exhibiting minimal exposed aluminum surfaces mechanically snap locking the multicellular to facilitate movement. (Material shall conform to ASTM 6063)
- Item number
- 5.45.1
- Analysis basis
- Details of Cost of 1 metre.
- Priced inputs
- 6
- Derived rate
- ₹5,305.65/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.45.1 (Providing and fixing of expansion joint system related with wall joint (internal/external) location as per drawings and direction of Engineer-InCharge. The joints shall be of extruded aluminum base members, self aligning / centering arrangement and support plates as per ASTM B22102. The material shall be such that it provides an Expansion Joints System suitable for vertical wall to wall/ wall to corner application, both new and existing construction in office Buildings & complexes with no slipping down tendency amongst the components of the Joint System. The Joint System shall utilize light weight aluminum profiles exhibiting minimal exposed aluminum surfaces mechanically snap locking the multicellular to facilitate movement. (Material shall conform to ASTM 6063) Wall Joint of 100 mm gap) is derived from 6 priced inputs and works out to ₹5,305.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIALS :
- LABOUR :
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2409 | MAT | Wall Joint of 100 mm | metre | 1 | 2,521.00 | 2,521.00 |
| 2402 | MAT | Epoxy adhesive | kg | 4.25 | 160.00 | 680.00 |
| 9977 | MAT | Carriage | L.S. | 124.9 | 2.27 | 283.52 |
| 0102 | LAB | Blacksmith 1st class | day | 0.05 | 897.00 | 44.85 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.1 | 897.00 | 89.70 |
| 0114 | LAB | Beldar | day | 0.15 | 736.00 | 110.40 |
- TOTAL
- 3,729.47
- Add 1 % Water charges on “W”
- +37.29
- TOTAL
- 3,766.76
- Add GST on “X” (multiplying factor 0.2127)
- +801.19
- TOTAL
- 4,567.95
- Add 15% CPOH on “Y”
- +685.19
- TOTAL
- 5,253.14
- Add Cess @ 1% on “Z”
- +52.53
- Cost of 1 metre.
- 5,305.67
- SAY
- ₹5,305.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 292
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 292. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.