Skip to main content

Providing and fixing of expansion joint system related with floor location as per drawings and direction of Engineer-In-Charge. The joints system will be of extruded aluminum base members, self aligning / self centering arrangement and support plates etc. as per ASTM B221-02. The system shall be such that it provides floor to floor /floor to wall expansion control system for various vertical localtion in load application areas that accommodates multi directional seismic movement without stress to it’s components. System shall consist of metal profiles with an universal aluminum base member designed to accommodate various project conditions and finish floor treatments. The cover plate shall be designed of width and thickness required to satisfy projects movement and loading requirements and secured to base members by utilizing manufacturer’s pre-engineered selfcentering arrangement that freely rotates / moves in all directions. The Self - centering arrangement shall exhibit circular sphere ends that lock and slide inside the corresponding aluminum extrusion cavity to allow freedom of movement and flexure in all directions including vertical displacement. Provision of Moisture Barrier Membrane in the Joint System to have watertight joint is mandatory requirement all as per the manufactures design and as approved by Engineer -in-Charge. (Material shall conform to ASTM 6063)

Floor Joint of 150 mm gap
Item number
5.44.2
Analysis basis
Details of Cost of 1 metre.
Priced inputs
6
Derived rate
₹7,812.35/ METRE
D-01/RATE ANALYSISITEM 5.44.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.44.2 (Providing and fixing of expansion joint system related with floor location as per drawings and direction of Engineer-In-Charge. The joints system will be of extruded aluminum base members, self aligning / self centering arrangement and support plates etc. as per ASTM B221-02. The system shall be such that it provides floor to floor /floor to wall expansion control system for various vertical localtion in load application areas that accommodates multi directional seismic movement without stress to it’s components. System shall consist of metal profiles with an universal aluminum base member designed to accommodate various project conditions and finish floor treatments. The cover plate shall be designed of width and thickness required to satisfy projects movement and loading requirements and secured to base members by utilizing manufacturer’s pre-engineered selfcentering arrangement that freely rotates / moves in all directions. The Self - centering arrangement shall exhibit circular sphere ends that lock and slide inside the corresponding aluminum extrusion cavity to allow freedom of movement and flexure in all directions including vertical displacement. Provision of Moisture Barrier Membrane in the Joint System to have watertight joint is mandatory requirement all as per the manufactures design and as approved by Engineer -in-Charge. (Material shall conform to ASTM 6063) Floor Joint of 150 mm gap) is derived from 6 priced inputs and works out to ₹7,812.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIALS :
  • LABOUR :
ANALYSIS OF RATES · ITEM 5.44.2DETAILS OF COST OF 1 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2404MATFloor Joint of 150 mmmetre14,243.004,243.00
2402MATEpoxy adhesivekg4.5160.00720.00
9977MATCarriageL.S.124.92.27283.52
0102LABBlacksmith 1st classday0.05897.0044.85
0123LABMason 1st classMason 1st classday0.1897.0089.70
0114LABBeldarday0.15736.00110.40
BUILD-UP TO RATE
TOTAL
5,491.47
Add 1 % Water charges on “W”
+54.91
TOTAL
5,546.38
Add GST on “X” (multiplying factor 0.2127)
+1,179.72
TOTAL
6,726.10
Add 15% CPOH on “Y”
+1,008.92
TOTAL
7,735.02
Add Cess @ 1% on “Z”
+77.35
Cost of 1 metre.
7,812.37
SAY
₹7,812.35
D-02/SOURCEPRINTED PAGE 291
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
291

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 291. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.