CPWD Analysis of Rates · Reinforced Cement Concrete

Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement All works upto plinth level

Concrete of M40 grade with minimum cement content of 390 kg/cum

Item number
5.33.1.4
Analysis basis
Details of cost for 1.00 cum
Priced inputs
12
Derived rate
9,957.65 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.33.1.4 Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement All works upto plinth level Concrete of M40 grade with minimum cement content of 390 kg/cum — is derived from 12 priced inputs for 1.00 cum and works out to ₹9,957.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Production cost, pumping to respective floors
  • and laying in position
  • Labour for pouring, consolidating & curing
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.571,425.00812.25
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.281,400.00392.00
0982Coarse sand (zone III)Materialcum0.4251,450.00616.25
0367Ordinary/Pozzolana/Slag CementPortland Cement (OPC-43 Grade)Materialtonne0.395,156.002,010.84
7318Plasticizer / super plasticizer(0.50% of cement)Plasticizer / super plasticizerMaterialgram1.9530.0058.50
0004Production cost of concrete by batch mix plant / ready mixed plantProduction cost of concrete by batch mix plantMachinerycum1450.00450.00
0009Pumping charges of concrete including hire charges of pump, carriage charges for all leads,piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinerycum1250.00250.00
0155Mason (average)Labourday0.17857.00145.69
0114BeldarLabourday2736.001,472.00
0101BhistiLabourday0.9816.00734.40
0012Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machineryday0.07400.0028.00
9999SundriesMaterialL.S.132.2729.51
TOTAL
6,999.44
Add 1 % Water charges on “W”
69.99
TOTAL
7,069.43
Add GST on “X” (multiplying factor 0.2127)
1,503.67
TOTAL
8,573.10
Add 15% CPOH on “Y”
1,285.97
TOTAL
9,859.07
Add Cess @ 1% on “Z”
98.59
Cost per 1.00 cum
9,957.66
Say
9,957.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 277. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.