Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Extra for laying reinforced cement concrete in or under foul positions

Item number
5.32
Analysis basis
Details of cost for 1 cum.
Priced inputs
4
Derived rate
467.55 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.32 Extra for laying reinforced cement concrete in or under foul positions — is derived from 4 priced inputs for 1 cum and works out to ₹467.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • ANALYSIS SAME AS ITEM NO 4.16
  • Extra labour due to slow progress-
CodeInputUnitQuantityRate (INR)Amount (INR)
0123Mason 1st classMason 1st classLabourday0.02897.0017.94
0124Mason 2nd classMason 2nd classLabourday0.02816.0016.32
0114BeldarLabourday0.25736.00184.00
0115CoolieLabourday0.15736.00110.40
TOTAL
328.66
Add 1 % Water charges on “W”
3.29
TOTAL
331.95
Add GST on “X” (multiplying factor 0.2127)
70.61
TOTAL
402.56
Add 15% CPOH on “Y”
60.38
TOTAL
462.94
Add Cess @ 1% on “Z”
4.63
Cost for 1 cum.
467.57
Say
467.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 274. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works