CPWD Analysis of Rates · Reinforced Cement Concrete
Add for plaster drip course/ groove in plastered surface or moulding to R.C.C. projections
- Item number
- 5.30
- Analysis basis
- Details of cost for 30 metre long throating or
- Priced inputs
- 4
- Derived rate
- ₹78.40 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.30 — Add for plaster drip course/ groove in plastered surface or moulding to R.C.C. projections — is derived from 4 priced inputs for 30 metre and works out to ₹78.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- plaster or moulding-
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0123 | Mason 1st classMason 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.5 | 816.00 | 408.00 |
| 0115 | CoolieLabour | day | 1 | 736.00 | 736.00 |
| 9999 | Add for materials (cement mortar etc.)Material | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 1,653.59
- Add 1 % Water charges on “W”
- 16.54
- TOTAL
- 1,670.13
- Add GST on “X” (multiplying factor 0.2127)
- 355.24
- TOTAL
- 2,025.37
- Add 15% CPOH on “Y”
- 303.81
- TOTAL
- 2,329.18
- Add Cess @ 1% on “Z”
- 23.29
- Cost for 30 metre
- 2,352.47
- Cost per metre
- 78.42
- Say
- 78.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 273. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.