CPWD Analysis of Rates · Reinforced Cement Concrete
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level
Hard drawn steel wire fabric
- Item number
- 5.22A.5
- Analysis basis
- Details of cost for 1 quintal-
- Priced inputs
- 5
- Derived rate
- ₹102.20 / Kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.22A.5 — Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level Hard drawn steel wire fabric — is derived from 5 priced inputs for 1 quintal and works out to ₹102.20 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- Hard drawn steel wire fabric 100kg,
- 7.75kg per sqm = 12.903 sqm.
- Total =13.548 sqm
- For cutting and laying in position.
- Add 5% wastage
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1021 | Hard drawn steel wire fabricHard drawn steel wire fabric 75 x 25 mm mesh of weight not less than 7.75 kg/sqmMaterial | sqm | 13.548 | 430.00 | 5,825.64 |
| 9999 | Cover blockMaterial | L.S. | 26 | 2.27 | 59.02 |
| 0103 | Blacksmith 2nd classLabour | day | 0.2 | 816.00 | 163.20 |
| 0114 | BeldarLabour | day | 1.5 | 736.00 | 1,104.00 |
| 9999 | Sundries and binding wireMaterial | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 7,182.55
- Add 1 % Water charges on “W”
- 71.83
- TOTAL
- 7,254.38
- Add GST on “X” (multiplying factor 0.2127)
- 1,543.01
- TOTAL
- 8,797.39
- Add 15% CPOH on “Y”
- 1,319.61
- TOTAL
- 10,117.00
- Add Cess @ 1% on “Z”
- 101.17
- Cost of one quintal
- 10,218.17
- Cost of 1 Kg.
- 102.18
- Say
- 102.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 264. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.