Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level

Mild steel and Medium Tensile steel bars

Item number
5.22A.1
Analysis basis
Details of cost for 1 quintal-
Priced inputs
5
Derived rate
107.10 / Kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.22A.1 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level Mild steel and Medium Tensile steel bars — is derived from 5 priced inputs for 1 quintal and works out to ₹107.10 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • Mild steel bars = 1.00 q
  • Wastage 5% = 0.05 q
  • Total = 1.05 q
  • For straightening, cutting, bending, binding
  • and placing in position-
CodeInputUnitQuantityRate (INR)Amount (INR)
1004Average rate of Mild steel round bars for reinforcementsAverage rate of Mild steel round bars for reinforcementMaterialquintal1.055,500.005,775.00
9999Cover blockMaterialL.S.262.2759.02
0102Blacksmith 1st classLabourday1897.00897.00
0114BeldarLabourday1736.00736.00
9999Sundries and binding wireMaterialL.S.26.912.2761.09
TOTAL
7,528.11
Add 1 % Water charges on “W”
75.28
TOTAL
7,603.39
Add GST on “X” (multiplying factor 0.2127)
1,617.24
TOTAL
9,220.63
Add 15% CPOH on “Y”
1,383.09
TOTAL
10,603.72
Add Cess @ 1% on “Z”
106.04
Cost of one quintal
10,709.76
Cost of 1 Kg.
107.10
Say
107.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 262. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works