CPWD Analysis of Rates · Reinforced Cement Concrete
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level
Mild steel and Medium Tensile steel bars
- Item number
- 5.22A.1
- Analysis basis
- Details of cost for 1 quintal-
- Priced inputs
- 5
- Derived rate
- ₹107.10 / Kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.22A.1 — Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level Mild steel and Medium Tensile steel bars — is derived from 5 priced inputs for 1 quintal and works out to ₹107.10 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- Mild steel bars = 1.00 q
- Wastage 5% = 0.05 q
- Total = 1.05 q
- For straightening, cutting, bending, binding
- and placing in position-
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1004 | Average rate of Mild steel round bars for reinforcementsAverage rate of Mild steel round bars for reinforcementMaterial | quintal | 1.05 | 5,500.00 | 5,775.00 |
| 9999 | Cover blockMaterial | L.S. | 26 | 2.27 | 59.02 |
| 0102 | Blacksmith 1st classLabour | day | 1 | 897.00 | 897.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 9999 | Sundries and binding wireMaterial | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 7,528.11
- Add 1 % Water charges on “W”
- 75.28
- TOTAL
- 7,603.39
- Add GST on “X” (multiplying factor 0.2127)
- 1,617.24
- TOTAL
- 9,220.63
- Add 15% CPOH on “Y”
- 1,383.09
- TOTAL
- 10,603.72
- Add Cess @ 1% on “Z”
- 106.04
- Cost of one quintal
- 10,709.76
- Cost of 1 Kg.
- 107.10
- Say
- 107.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 262. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works