Skip to main content

CPWD Analysis of Rates · Rain Water Harvesting & Tube Wells

Supplying, assembling, lowering and fixing in vertical position in bore well unplasticized PVC medium well screen (RMS) pipes with ribs, conforming to IS: 12818, including hire & labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineerin-charge

150 mm nominal size dia

Item number
23.4.2
Analysis basis
Details of cost for 100 metres
Priced inputs
4
Derived rate
807.45 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.4.2 Supplying, assembling, lowering and fixing in vertical position in bore well unplasticized PVC medium well screen (RMS) pipes with ribs, conforming to IS: 12818, including hire & labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineerin-charge 150 mm nominal size dia — is derived from 4 priced inputs for 100 metres and works out to ₹807.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7751uPVC slotted pipe 150 mm dia as per IS: 12818PVC slotted pipe 150 mm dia as per IS: 12818Materialmetre100560.0056,000.00
0114BeldarLabourday0.5736.00368.00
0115CoolieLabourday0.5736.00368.00
9999Sundries (Adhesive etc.)MaterialL.S.10.072.2722.86
TOTAL
56,758.86
Add 1 % Water charges on “W”
567.59
TOTAL
57,326.45
Add GST on “X” (multiplying factor 0.2127)
12,193.34
TOTAL
69,519.79
Add 15% CPOH on “Y”
10,427.97
TOTAL
79,947.76
Add Cess @ 1% on “Z”
799.48
Cost of 100 metres
80,747.24
Cost of 1 metre
807.47
Say
807.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1876. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.