Skip to main content

Supplying, assembling, lowering and fixing in vertical position in bore well unplasticized PVC medium well screen (RMS) pipes with ribs, conforming to IS: 12818, including hire & labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineerin-charge

150 mm nominal size dia
Item number
23.4.2
Analysis basis
100 metres
Priced inputs
4
Derived rate
₹807.45/ METRE
D-01/RATE ANALYSISITEM 23.4.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.4.2 (Supplying, assembling, lowering and fixing in vertical position in bore well unplasticized PVC medium well screen (RMS) pipes with ribs, conforming to IS: 12818, including hire & labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineerin-charge 150 mm nominal size dia) is derived from 4 priced inputs for 100 metres and works out to ₹807.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 23.4.2DETAILS OF COST FOR 100 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7751MATuPVC slotted pipe 150 mm dia as per IS: 12818PVC slotted pipe 150 mm dia as per IS: 12818metre100560.0056,000.00
0114LABBeldarday0.5736.00368.00
0115LABCoolieday0.5736.00368.00
9999MATSundries (Adhesive etc.)L.S.10.072.2722.86
BUILD-UP TO RATE
TOTAL
56,758.86
Add 1 % Water charges on “W”
+567.59
TOTAL
57,326.45
Add GST on “X” (multiplying factor 0.2127)
+12,193.34
TOTAL
69,519.79
Add 15% CPOH on “Y”
+10,427.97
TOTAL
79,947.76
Add Cess @ 1% on “Z”
+799.48
Cost of 100 metres
80,747.24
Cost of 1 metre
807.47
SAY
₹807.45
D-02/SOURCEPRINTED PAGE 1876
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1876

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1876. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSRAIN WATER HARVESTING & TUBE WELLS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.