CPWD Analysis of Rates · Rain Water Harvesting & Tube Wells
Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level All types of soil
400 mm dia
- Item number
- 23.2.1.3
- Analysis basis
- Details of cost for 20 metre
- Priced inputs
- 7
- Derived rate
- ₹1,238.50 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.2.1.3 — Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level All types of soil 400 mm dia — is derived from 7 priced inputs for 20 metre and works out to ₹1,238.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- MACHINERY :
- Transportation charges for to and fro to site
- (assume 140m of bore for one shifting) (2
- x30)/140
- Loading, unloading &Errection charges of drilling Rig Machine
- Extra labour to assist M/C operator &security
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0020 | Hydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuelMachinery | day | 1 | 7,850.00 | 7,850.00 |
| 0005 | Hire charges of Diesel Truck - 9 tonneHire charges of Diesel Truck - 9 tonne (with POL)Machinery | day | 0.429 | 4,400.00 | 1,887.60 |
| 0114 | BeldarLabour | day | 4 | 736.00 | 2,944.00 |
| 0130 | MistryLabour | day | 1 | 897.00 | 897.00 |
| 7763 | Water supply tanker of 5000 litre capacityMaterial | each | 1 | 1,625.00 | 1,625.00 |
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 0113 | ChowkidarLabour | day | 1 | 736.00 | 736.00 |
- TOTAL
- 17,411.60
- Add 1 % Water charges on “W”
- 174.12
- TOTAL
- 17,585.72
- Add GST on “X” (multiplying factor 0.2127)
- 3,740.48
- TOTAL
- 21,326.20
- Add 15% CPOH on “Y”
- 3,198.93
- TOTAL
- 24,525.13
- Add Cess @ 1% on “Z”
- 245.25
- Cost for 20 metre
- 24,770.38
- Cost of 1 metre
- 1,238.52
- Say
- 1,238.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1872. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.