CPWD Analysis of Rates · Rain Water Harvesting & Tube Wells

Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level All types of soil

300 mm dia

Item number
23.2.1.1
Analysis basis
Details of cost for 30 metre
Priced inputs
7
Derived rate
825.70 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.2.1.1 Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level All types of soil 300 mm dia — is derived from 7 priced inputs for 30 metre and works out to ₹825.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • MACHINERY :
  • Transportation charges for to and fro to site
  • (assume 140m of bore for one shifting) (2
  • x30)/140
  • Loading, unloading &Errection charges of drilling Rig Machine
  • Extra labour to assist M/C operator &security
CodeInputUnitQuantityRate (INR)Amount (INR)
0020Hydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuelMachineryday17,850.007,850.00
0005Hire charges of Diesel Truck - 9 tonneHire charges of Diesel Truck - 9 tonne (with POL)Machineryday0.4294,400.001,887.60
0114BeldarLabourday4736.002,944.00
0130MistryLabourday1897.00897.00
7763Water supply tanker of 5000 litre capacityMaterialeach11,625.001,625.00
0114BeldarLabourday2736.001,472.00
0113ChowkidarLabourday1736.00736.00
TOTAL
17,411.60
Add 1 % Water charges on “W”
174.12
TOTAL
17,585.72
Add GST on “X” (multiplying factor 0.2127)
3,740.48
TOTAL
21,326.20
Add 15% CPOH on “Y”
3,198.93
TOTAL
24,525.13
Add Cess @ 1% on “Z”
245.25
Cost for 30 metre
24,770.38
Cost of 1 metre
825.68
Say
825.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1870. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.