Providing and fixing Bail plug/ Bottom plug of required dia to the bottom of pipe assembly of tubewell as per IS:2800 (part I)

200 mm dia
Item number
23.15.3
Analysis basis
1 No
Priced inputs
2
Derived rate
₹357.60/ NO
D-01/RATE ANALYSISITEM 23.15.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.15.3 (Providing and fixing Bail plug/ Bottom plug of required dia to the bottom of pipe assembly of tubewell as per IS:2800 (part I) 200 mm dia) is derived from 2 priced inputs for 1 No and works out to ₹357.60 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 23.15.3DETAILS OF COST FOR 1 NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7750MATM.S bail plug 200 mm diaeach1240.00240.00
9999MATSundriesL.S.52.2711.35
BUILD-UP TO RATE
TOTAL
251.35
Add 1 % Water charges on “W”
+2.51
TOTAL
253.86
Add GST on “X” (multiplying factor 0.2127)
+54.00
TOTAL
307.86
Add 15% CPOH on “Y”
+46.18
TOTAL
354.04
Add Cess @ 1% on “Z”
+3.54
Cost of 1 No
357.58
SAY
₹357.60
D-02/SOURCEPRINTED PAGE 1885
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1885

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1885. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSRAIN WATER HARVESTING & TUBE WELLS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.