Skip to main content

CPWD Analysis of Rates · Rain Water Harvesting & Tube Wells

Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer-in-charge, upto 90 metre depth below ground level Rocky strata including Boulders

350 mm dia

Item number
23.1.2.2
Analysis basis
Details of cost for 16 metre
Priced inputs
10
Derived rate
1,792.85 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.1.2.2 Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer-in-charge, upto 90 metre depth below ground level Rocky strata including Boulders 350 mm dia — is derived from 10 priced inputs for 16 metre and works out to ₹1,792.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • MACHINERY :
  • Extra diesel required for boring in rockystrata
  • Transportation charges for to and fro to site
  • (assume 140m of bore for one shifting) (2
  • x30)/140
  • Loading, unloading &Errection charges of drilling Rig Machine
  • Extra labour to assist M/C operator &security
CodeInputUnitQuantityRate (INR)Amount (INR)
0020Hydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuelMachineryday0.97,850.007,065.00
1235Diesel oilDieselMateriallitre889.62716.96
0005Hire charges of Diesel Truck - 9 tonneHire charges of Diesel Truck - 9 tonne (with POL)Machineryday0.4294,400.001,887.60
0114BeldarLabourday4736.002,944.00
0130MistryLabourday1897.00897.00
7763Water supply tanker of 5000 litre capacityMaterialeach11,625.001,625.00
0134Rock Hole DrillerLabourday1736.00736.00
0114BeldarLabourday4736.002,944.00
0103Blacksmith 2nd classLabourday0.75816.00612.00
0113ChowkidarLabourday1736.00736.00
TOTAL
20,163.56
Add 1 % Water charges on “W”
201.64
TOTAL
20,365.20
Add GST on “X” (multiplying factor 0.2127)
4,331.68
TOTAL
24,696.88
Add 15% CPOH on “Y”
3,704.53
TOTAL
28,401.41
Add Cess @ 1% on “Z”
284.01
Cost for 16 metre
28,685.42
Cost of 1 metre
1,792.84
Say
1,792.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1869. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works