Skip to main content

Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer-in-charge, upto 90 metre depth below ground level All types of soil

400 mm dia
Item number
23.1.1.3
Analysis basis
25 metre
Priced inputs
7
Derived rate
₹990.80/ METRE
D-01/RATE ANALYSISITEM 23.1.1.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.1.1.3 (Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer-in-charge, upto 90 metre depth below ground level All types of soil 400 mm dia) is derived from 7 priced inputs for 25 metre and works out to ₹990.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MACHINERY :
  • Transportation charges for to and fro to site
  • (assume 140m of bore for one shifting) (2
  • x30)/140
  • Loading, unloading &Errection charges of drilling Rig Machine
  • Extra labour to assist M/C operator & security
ANALYSIS OF RATES · ITEM 23.1.1.3DETAILS OF COST FOR 25 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0020MACHHydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuelday17,850.007,850.00
0005MACHHire charges of Diesel Truck - 9 tonneHire charges of Diesel Truck - 9 tonne (with POL)day0.4294,400.001,887.60
0114LABBeldarday4736.002,944.00
0130LABMistryday1897.00897.00
7763MATWater supply tanker of 5000 litre capacityeach11,625.001,625.00
0114LABBeldarday2736.001,472.00
0113LABChowkidarday1736.00736.00
BUILD-UP TO RATE
TOTAL
17,411.60
Add 1 % Water charges on “W”
+174.12
TOTAL
17,585.72
Add GST on “X” (multiplying factor 0.2127)
+3,740.48
TOTAL
21,326.20
Add 15% CPOH on “Y”
+3,198.93
TOTAL
24,525.13
Add Cess @ 1% on “Z”
+245.25
Cost for 25 metre
24,770.38
Cost of 1 metre
990.82
SAY
₹990.80
D-02/SOURCEPRINTED PAGE 1868
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1868

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1868. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSRAIN WATER HARVESTING & TUBE WELLS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.