CPWD Analysis of Rates · Pile Work

Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/Anchor piles method and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of Engineer in-charge Single pile upto 50 tonne Safe capacity

Routine test (Test Load 1.5 times the Safe capacity)

Item number
20.6.1.2
Analysis basis
Details of cost for 1 test
Priced inputs
1
Derived rate
19,632.40 / test

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.6.1.2 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/Anchor piles method and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of Engineer in-charge Single pile upto 50 tonne Safe capacity Routine test (Test Load 1.5 times the Safe capacity) — is derived from 1 priced inputs for 1 test and works out to ₹19,632.40 per test after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7249Cyclic verticle load testing of piles in accordance with IS : 2911 (Part-IV) including prepration of pile head etc. for Single pile upto 50 tonne capacityCyclic vertical load testing of piles in accordance with IS : 2911 (Part- IV) including preparation of pile head etc. for Single pile up to 50 tonne capacityMaterialper test113,800.0013,800.00
TOTAL
13,800.00
Add 1 % Water charges on “W”
138.00
TOTAL
13,938.00
Add GST on “X” (multiplying factor 0.2127)
2,964.61
TOTAL
16,902.61
Add 15% CPOH on “Y”
2,535.39
TOTAL
19,438.00
Add Cess @ 1% on “Z”
194.38
Cost per test
19,632.38
Say
19,632.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1807. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.