CPWD Analysis of Rates · Pile Work
Extra over single under ream for providing additional bulbs in under reamed piles, under specified diameter(only the nos. of extra bulbs are to be paid)
450 mm dia piles
- Item number
- 20.4.3
- Analysis basis
- Details of cost for 1 bulb.
- Priced inputs
- 7
- Derived rate
- ₹3,104.20 / bulb
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.4.3 — Extra over single under ream for providing additional bulbs in under reamed piles, under specified diameter(only the nos. of extra bulbs are to be paid) 450 mm dia piles — is derived from 7 priced inputs for 1 bulb and works out to ₹3,104.20 per bulb after water charges, GST, CPOH and cess. The full build-up is below.
- Bulb - 0.081 cum
- Work supervisor
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1Sub-analysis | cum | 0.081 | 9,504.75 | 769.88 | |
| 7183 | BentoniteBentonite of 35 kg per pileMaterial | tonne | 0.008 | 3,050.00 | 24.40 |
| 0024 | Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at siteMachinery | day | 0.02 | 39,500.00 | 790.00 |
| 0025 | Hire and running charges of light crane.Hire and running charges of light craneMachinery | day | 0.01 | 3,900.00 | 39.00 |
| 0026 | Hire and running charges of bentonite pumpMachinery | day | 0.01 | 3,350.00 | 33.50 |
| 0130 | MistryLabour | day | 0.02 | 897.00 | 17.94 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
- Total
- 2,410.72
- Add 1% water charges on “W -A”
- 16.41
- TOTAL
- 2,427.13
- Add GST on “X-A” (multiplying factor 0.2127)
- 352.50
- TOTAL
- 2,779.63
- Add 15% CP & OH on “Y-A”
- 301.46
- TOTAL
- 3,081.09
- Add 1% cess on “Z -A”
- 23.11
- Cost of 1 bulb
- 3,104.20
- Say
- 3,104.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1801. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.