Extra over single under ream for providing additional bulbs in under reamed piles, under specified diameter(only the nos. of extra bulbs are to be paid)

450 mm dia piles
Item number
20.4.3
Analysis basis
1 bulb
Priced inputs
7
Derived rate
₹3,104.20/ BULB
D-01/RATE ANALYSISITEM 20.4.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.4.3 (Extra over single under ream for providing additional bulbs in under reamed piles, under specified diameter(only the nos. of extra bulbs are to be paid) 450 mm dia piles) is derived from 7 priced inputs for 1 bulb and works out to ₹3,104.20 per bulb after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Bulb - 0.081 cum
  • Work supervisor
ANALYSIS OF RATES · ITEM 20.4.3DETAILS OF COST FOR 1 BULB
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1cum0.0819,504.75769.88
7183MATBentoniteBentonite of 35 kg per piletonne0.0083,050.0024.40
0024MACHHire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at siteday0.0239,500.00790.00
0025MACHHire and running charges of light crane.Hire and running charges of light craneday0.013,900.0039.00
0026MACHHire and running charges of bentonite pumpday0.013,350.0033.50
0130LABMistryday0.02897.0017.94
0114LABBeldarday1736.00736.00
BUILD-UP TO RATE
Total
2,410.72
Add 1% water charges on “W -A”
+16.41
TOTAL
2,427.13
Add GST on “X-A” (multiplying factor 0.2127)
+352.50
TOTAL
2,779.63
Add 15% CP & OH on “Y-A”
+301.46
TOTAL
3,081.09
Add 1% cess on “Z -A”
+23.11
Cost of 1 bulb
3,104.20
SAY
₹3,104.20
D-02/SOURCEPRINTED PAGE 1801
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1801

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1801. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.