Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap)
- Item number
- 20.3.4
- Analysis basis
- 10 metres
- Priced inputs
- 8
- Derived rate
- ₹4,721.15/ METRES
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.3.4 (Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap) : 550 mm dia piles) is derived from 8 priced inputs for 10 metres and works out to ₹4,721.15 per metres after water charges, GST, CPOH and cess. The full build-up is below.
- RCC- Stem -3.14/4x(0.50)²x9.125 = 1.792
- cum, Bulb -3.14/4x(1.25)²x0.125 = 0.153
- cum, 2x 3.14/4x(0.875)²x0.375 = 0.451
- cum, Total = 2.396 cum say 2.40 cum
- Work supervisor
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1 | cum | 2.4 | 9,504.75 | 22,811.40 | |
| 7183 | MAT | BentoniteBentonite of 35 kg per pile | tonne | 0.2 | 3,050.00 | 610.00 |
| 9999 | MAT | Sundries | L.S. | 210 | 2.27 | 476.70 |
| 0024 | MACH | Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at site | day | 0.36 | 39,500.00 | 14,220.00 |
| 0025 | MACH | Hire and running charges of light crane.Hire and running charges of light crane | day | 0.06 | 3,900.00 | 234.00 |
| 0026 | MACH | Hire and running charges of bentonite pump | day | 0.02 | 3,350.00 | 67.00 |
| 0130 | LAB | Mistry | day | 0.08 | 897.00 | 71.76 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
- Total
- 39,962.86
- Add 1% water charges on “W -A”
- +171.51
- TOTAL
- 40,134.37
- Add GST on “X-A” (multiplying factor 0.2127)
- +3,684.60
- TOTAL
- 43,818.97
- Add 15% CP & OH on “Y-A”
- +3,151.14
- TOTAL
- 46,970.11
- Add 1% cess on “Z -A”
- +241.59
- Cost of 10 m pile
- 47,211.70
- Cost for 1 m pile
- 4,721.17
- SAY
- ₹4,721.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1799
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1799. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.