Skip to main content

CPWD Analysis of Rates · Pile Work

Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap)

400 mm dia piles

Item number
20.3.2
Analysis basis
Details of cost for 10 metres
Priced inputs
8
Derived rate
3,797.30 / metres

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.3.2 Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap) : 400 mm dia piles — is derived from 8 priced inputs for 10 metres and works out to ₹3,797.30 per metres after water charges, GST, CPOH and cess. The full build-up is below.

  • RCC - Stem
  • - 3.14/4x(0.40)²x9.30 = 1.169 cu
  • m Bulb 3.14/4x(1.00)²x0.1 = 0.079 cum
  • 2x 3.14/4x(0.7)²x0.30 = 0.23 cum,
  • Total= 1.478 cum
  • Work supervisor
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1Sub-analysiscum1.4789,504.7514,048.02
7183BentoniteBentonite of 35 kg per pileMaterialtonne0.153,050.00457.50
9999SundriesMaterialL.S.1302.27295.10
0024Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at siteMachineryday0.3639,500.0014,220.00
0025Hire and running charges of light crane.Hire and running charges of light craneMachineryday0.063,900.00234.00
0026Hire and running charges of bentonite pumpMachineryday0.023,350.0067.00
0130MistryLabourday0.08897.0071.76
0114BeldarLabourday2736.001,472.00
Total
30,865.38
Add 1% water charges on “W -A”
168.17
TOTAL
31,033.55
Add GST on “X-A” (multiplying factor 0.2127)
3,612.82
TOTAL
34,646.37
Add 15% CP & OH on “Y-A”
3,089.75
TOTAL
37,736.12
Add 1% cess on “Z -A”
236.88
Cost of 10 m pile
37,973.00
Cost for 1 m pile
3,797.30
Say
3,797.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1797. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works