Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap)

400 mm dia piles
Item number
20.3.2
Analysis basis
10 metres
Priced inputs
8
Derived rate
₹3,797.30/ METRES
D-01/RATE ANALYSISITEM 20.3.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.3.2 (Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap) : 400 mm dia piles) is derived from 8 priced inputs for 10 metres and works out to ₹3,797.30 per metres after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • RCC - Stem
  • - 3.14/4x(0.40)²x9.30 = 1.169 cu
  • m Bulb 3.14/4x(1.00)²x0.1 = 0.079 cum
  • 2x 3.14/4x(0.7)²x0.30 = 0.23 cum,
  • Total= 1.478 cum
  • Work supervisor
ANALYSIS OF RATES · ITEM 20.3.2DETAILS OF COST FOR 10 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1cum1.4789,504.7514,048.02
7183MATBentoniteBentonite of 35 kg per piletonne0.153,050.00457.50
9999MATSundriesL.S.1302.27295.10
0024MACHHire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at siteday0.3639,500.0014,220.00
0025MACHHire and running charges of light crane.Hire and running charges of light craneday0.063,900.00234.00
0026MACHHire and running charges of bentonite pumpday0.023,350.0067.00
0130LABMistryday0.08897.0071.76
0114LABBeldarday2736.001,472.00
BUILD-UP TO RATE
Total
30,865.38
Add 1% water charges on “W -A”
+168.17
TOTAL
31,033.55
Add GST on “X-A” (multiplying factor 0.2127)
+3,612.82
TOTAL
34,646.37
Add 15% CP & OH on “Y-A”
+3,089.75
TOTAL
37,736.12
Add 1% cess on “Z -A”
+236.88
Cost of 10 m pile
37,973.00
Cost for 1 m pile
3,797.30
SAY
₹3,797.30
D-02/SOURCEPRINTED PAGE 1797
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1797

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1797. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSPILE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.