Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used

1500 mm dia piles
Item number
20.2A.5
Analysis basis
9 m
Priced inputs
10
Derived rate
₹24,408.80/ M
D-01/RATE ANALYSISITEM 20.2A.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.2A.5 (Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used 1500 mm dia piles) is derived from 10 priced inputs for 9 m and works out to ₹24,408.80 per m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Concrete 3.14/4x1.50²x9 = 15.90 cum
  • Work supervisor
ANALYSIS OF RATES · ITEM 20.2A.5DETAILS OF COST FOR 9 M LENGTH OF PILE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1cum15.99,504.751,51,125.53
7183MATBentoniteBentonite of 35 kg per piletonne0.453,050.001,372.50
9999MATSundriesL.S.3152.27715.05
0024MACHHire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at siteday0.7739,500.0030,415.00
0025MACHHire and running charges of light crane.Hire and running charges of light craneday0.13,900.00390.00
0026MACHHire and running charges of bentonite pumpday0.963,350.003,216.00
0018MACHHire and running charges of loaderday0.756,700.005,025.00
0017MACHHire and running charges of tipperday0.754,200.003,150.00
0130LABMistryday0.25897.00224.25
0114LABBeldarday5736.003,680.00
BUILD-UP TO RATE
Total
1,99,313.33
Add 1% water charges on “W -A”
+481.88
TOTAL
1,99,795.21
Add GST on “X-A” (multiplying factor 0.2127)
+10,352.04
TOTAL
2,10,147.25
Add 15% CP & OH on “Y-A”
+8,853.26
TOTAL
2,19,000.51
Add 1% cess on “Z -A”
+678.75
Cost of 9m pile
2,19,679.26
Cost for 1 m pile
24,408.81
SAY
₹24,408.80
D-02/SOURCEPRINTED PAGE 1796
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1796

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1796. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSPILE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.