Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by percussion drilling using Direct mud circulation (DMC) or Bailer and chisel technique by tripod and mechanical Winch Machine all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tubewell boring machine shall not be used
- Item number
- 20.2.2
- Analysis basis
- 20 m
- Priced inputs
- 10
- Derived rate
- ₹2,703.25/ M
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.2.2 (Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by percussion drilling using Direct mud circulation (DMC) or Bailer and chisel technique by tripod and mechanical Winch Machine all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tubewell boring machine shall not be used 500 mm dia piles) is derived from 10 priced inputs for 20 m and works out to ₹2,703.25 per m after water charges, GST, CPOH and cess. The full build-up is below.
- Concrete 3.14/4x0.50²x20 = 3.925cum
- Work supervisor
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1 | cum | 3.925 | 9,504.75 | 37,306.14 | |
| 7183 | MAT | BentoniteBentonite of 35 kg per pile | tonne | 0.28 | 3,050.00 | 854.00 |
| 9999 | MAT | Sundries | L.S. | 80 | 2.27 | 181.60 |
| 0015 | MACH | Hire and running charges of Tripod and Mechanical Winch machine complete with power unit and accessories | day | 1.2 | 3,350.00 | 4,020.00 |
| 0025 | MACH | Hire and running charges of light crane.Hire and running charges of light crane | day | 0.06 | 3,900.00 | 234.00 |
| 0026 | MACH | Hire and running charges of bentonite pump | day | 0.38 | 3,350.00 | 1,273.00 |
| 0018 | MACH | Hire and running charges of loader | day | 0.3 | 6,700.00 | 2,010.00 |
| 0017 | MACH | Hire and running charges of tipper | day | 0.3 | 4,200.00 | 1,260.00 |
| 0130 | LAB | Mistry | day | 0.12 | 897.00 | 107.64 |
| 0114 | LAB | Beldar | day | 2.5 | 736.00 | 1,840.00 |
- Total
- 49,086.38
- Add 1% water charges on “W -A”
- +117.80
- TOTAL
- 49,204.18
- Add GST on “X-A” (multiplying factor 0.2127)
- +2,530.71
- TOTAL
- 51,734.89
- Add 15% CP & OH on “Y-A”
- +2,164.31
- TOTAL
- 53,899.20
- Add 1% cess on “Z -A”
- +165.93
- Cost of 20 m pile
- 54,065.13
- Cost for 1 m pile
- 2,703.26
- SAY
- ₹2,703.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1791
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1791. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.