Providing, driving with hydraulic piling rigs with power units and installing driven cast-insitu reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)
- Item number
- 20.1.1
- Analysis basis
- 20 m
- Priced inputs
- 8
- Derived rate
- ₹2,767.00/ M
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.1.1 (Providing, driving with hydraulic piling rigs with power units and installing driven cast-insitu reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap) : 400 mm dia piles) is derived from 8 priced inputs for 20 m and works out to ₹2,767.00 per m after water charges, GST, CPOH and cess. The full build-up is below.
- Concrete -3.14/4x0.40²x20 = 2.51 cum
- Work supervisor
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1 | cum | 2.51 | 9,504.75 | 23,856.92 | |
| 9999 | MAT | Sundries | L.S. | 175 | 2.27 | 397.25 |
| 7181 | MAT | C.I. pile shoe of 80 kg per pile @ 80 kg per pileC.I. pile shoe | kilogram | 80 | 52.00 | 4,160.00 |
| 7182 | MAT | M.S. clamps for pile shoe of 35 kg per pileM.S. clamps for pile shoe of 35 kg per pile | kilogram | 35 | 45.00 | 1,575.00 |
| 0024 | MACH | Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at site | day | 0.36 | 39,500.00 | 14,220.00 |
| 0025 | MACH | Hire and running charges of light crane.Hire and running charges of light crane | day | 0.06 | 3,900.00 | 234.00 |
| 0130 | LAB | Mistry | day | 0.08 | 897.00 | 71.76 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
- TOTAL
- 45,986.93
- Add 1% water charges on “W -A”
- +221.30
- TOTAL
- 46,208.23
- Add GST on “X-A” (multiplying factor 0.2127)
- +4,754.12
- TOTAL
- 50,962.35
- Add 15% CP & OH on “Y-A”
- +4,065.81
- TOTAL
- 55,028.16
- Add 1% cess on “Z -A”
- +311.71
- Cost of 20 m pile
- 55,339.87
- Cost for 1 m pile
- 2,766.99
- SAY
- ₹2,767.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1785
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1785. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.