Skip to main content

CPWD Analysis of Rates · New Technologies and Materials

Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tiestrips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge

Bi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse direction

Item number
26.85.1
Analysis basis
Details of Cost for 300 Sqm.
Priced inputs
4
Derived rate
229.65 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.85.1 Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tiestrips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge Bi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse direction — is derived from 4 priced inputs for 300 Sqm and works out to ₹229.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIALS:
  • ments geogrid for wastage and accessories
  • like tie-strips, nuts and bolts and loops/lungs
  • for joining reinforcing elements with the
  • facia panels, overlaps and other protective
  • elements for geogrid and all other activities
  • required to complete the item in all respect
  • LABOUR:
  • Add 5 percent of the cost of reinforcing ele-
CodeInputUnitQuantityRate (INR)Amount (INR)
8988Bi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse directionBi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse direction.Materialsqm300131.0039,300.00
0128MateLabourday0.36816.00293.76
0114BeldarLabourday6736.004,416.00
0139Skilled BeldarSkilled Beldar (for floor rubbing etc.)Labourday3816.002,448.00
including transportation.i.e 5% of (P)
1,965.00
Total
48,422.76
Add 1 % Water charges on “W”
484.23
TOTAL
48,906.99
Add GST on “X” (multiplying factor 0.2127)
10,402.52
TOTAL
59,309.51
Add 15% CPOH on “Y”
8,896.43
TOTAL
68,205.94
Add Cess @ 1% on “Z”
682.06
Cost of 300 sqm
68,888.00
Cost of 1 sqm
229.63
Say
229.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2030. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works