CPWD Analysis of Rates · New Technologies and Materials
Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge
Uni Axial Woven polyster geogrid of minimum tensile strength 250KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction
- Item number
- 26.84.8
- Analysis basis
- Details of Cost for 300 Sqm.
- Priced inputs
- 4
- Derived rate
- ₹819.65 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.84.8 — Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge Uni Axial Woven polyster geogrid of minimum tensile strength 250KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction — is derived from 4 priced inputs for 300 Sqm and works out to ₹819.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIALS:
- ments geogrid for wastage and accessories
- like tie-strips, nuts and bolts and loops/lungs
- for joining reinforcing elements with the
- facia panels, overlaps and other protective
- elements for geogrid and all other activities
- required to complete the item in all respect
- LABOUR:
- Add 5 percent of the cost of reinforcing ele-
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8986 | Uni Axial Woven polyster geogrid of minimum tensile strength 250KN/m in the Longitudinal direction and 30KN/m in the Transverse directionUni Axial Woven polyster geogrid of minimum tensile strength 250KN/m in the Longitudinal direction and 30KN/m in the Transverse direction.Material | sqm | 300 | 526.00 | 1,57,800.00 |
| 0128 | MateLabour | day | 0.36 | 816.00 | 293.76 |
| 0114 | BeldarLabour | day | 6 | 736.00 | 4,416.00 |
| 0139 | Skilled BeldarSkilled Beldar (for floor rubbing etc.)Labour | day | 3 | 816.00 | 2,448.00 |
- including transportation. i.e 5% of (P)
- 7,890.00
- Total
- 1,72,847.76
- Add 1 % Water charges on “W”
- 1,728.48
- TOTAL
- 1,74,576.24
- Add GST on “X” (multiplying factor 0.2127)
- 37,132.37
- TOTAL
- 2,11,708.61
- Add 15% CPOH on “Y”
- 31,756.29
- TOTAL
- 2,43,464.90
- Add Cess @ 1% on “Z”
- 2,434.65
- Cost of 300 sqm
- 2,45,899.55
- Cost of 1 sqm
- 819.67
- Say
- 819.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2029. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.