Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge
- Item number
- 26.84.2
- Analysis basis
- 300 Sqm
- Priced inputs
- 4
- Derived rate
- ₹310.30/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.84.2 (Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction) is derived from 4 priced inputs for 300 Sqm and works out to ₹310.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIALS:
- ments geogrid for wastage and accessories
- like tie-strips, nuts and bolts and loops/lungs
- for joining reinforcing elements with the
- facia panels, overlaps and other protective
- elements for geogrid and all other activities
- required to complete the item in all respect
- LABOUR:
- Add 5 percent of the cost of reinforcing ele-
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8980 | MAT | Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction | sqm | 300 | 185.00 | 55,500.00 |
| 0128 | LAB | Mate | day | 0.36 | 816.00 | 293.76 |
| 0114 | LAB | Beldar | day | 6 | 736.00 | 4,416.00 |
| 0139 | LAB | Skilled BeldarSkilled Beldar (for floor rubbing etc.) | day | 3 | 816.00 | 2,448.00 |
- including transportation.i.e 5% of (P)
- +2,775.00
- Total
- 65,432.76
- Add 1 % Water charges on “W”
- +654.33
- TOTAL
- 66,087.09
- Add GST on “X” (multiplying factor 0.2127)
- +14,056.72
- TOTAL
- 80,143.81
- Add 15% CPOH on “Y”
- +12,021.57
- TOTAL
- 92,165.38
- Add Cess @ 1% on “Z”
- +921.65
- Cost of 300 sqm
- 93,087.03
- Cost of 1 sqm
- 310.29
- SAY
- ₹310.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 2025
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2025. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.