Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge

Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction
Item number
26.84.2
Analysis basis
300 Sqm
Priced inputs
4
Derived rate
₹310.30/ SQM
D-01/RATE ANALYSISITEM 26.84.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.84.2 (Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction) is derived from 4 priced inputs for 300 Sqm and works out to ₹310.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIALS:
  • ments geogrid for wastage and accessories
  • like tie-strips, nuts and bolts and loops/lungs
  • for joining reinforcing elements with the
  • facia panels, overlaps and other protective
  • elements for geogrid and all other activities
  • required to complete the item in all respect
  • LABOUR:
  • Add 5 percent of the cost of reinforcing ele-
ANALYSIS OF RATES · ITEM 26.84.2DETAILS OF COST FOR 300 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8980MATUni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse directionsqm300185.0055,500.00
0128LABMateday0.36816.00293.76
0114LABBeldarday6736.004,416.00
0139LABSkilled BeldarSkilled Beldar (for floor rubbing etc.)day3816.002,448.00
BUILD-UP TO RATE
including transportation.i.e 5% of (P)
+2,775.00
Total
65,432.76
Add 1 % Water charges on “W”
+654.33
TOTAL
66,087.09
Add GST on “X” (multiplying factor 0.2127)
+14,056.72
TOTAL
80,143.81
Add 15% CPOH on “Y”
+12,021.57
TOTAL
92,165.38
Add Cess @ 1% on “Z”
+921.65
Cost of 300 sqm
93,087.03
Cost of 1 sqm
310.29
SAY
₹310.30
D-02/SOURCEPRINTED PAGE 2025
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2025

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2025. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.