Fabrication & Manufacturing of Prestressed Hollow Core slab (Hollow area 25 to 30%) of different thickness & modular width 1200 mm in Controlled Factory Environment with approved methodology conforming to IS 10297:1982 by using long line casting method having arrangement of proper steel bed. Concreting should be done by batch mixing plant capable of producing zero slump concrete, transported through automatic shuttels of standard make & layed on bed with the help of extruder/Slipformer, finishing, curing and also provision of steam curing. Cutting, making necessary cutout/holes of required sizes for services in slab element after achieving required strength, yard handling & stacking all complete as per approved shop drawings & design mix as per the direction of the Engineer-in-charge. (Cost of strands should be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately) Extra for using M-60 (Cement content 440 kg) instead of M-40

150mm thick hollow core slab
Item number
26.73.3.3
Priced inputs
2
Derived rate
₹44.20/ METRE
D-01/RATE ANALYSISITEM 26.73.3.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.73.3.3 (Fabrication & Manufacturing of Prestressed Hollow Core slab (Hollow area 25 to 30%) of different thickness & modular width 1200 mm in Controlled Factory Environment with approved methodology conforming to IS 10297:1982 by using long line casting method having arrangement of proper steel bed. Concreting should be done by batch mixing plant capable of producing zero slump concrete, transported through automatic shuttels of standard make & layed on bed with the help of extruder/Slipformer, finishing, curing and also provision of steam curing. Cutting, making necessary cutout/holes of required sizes for services in slab element after achieving required strength, yard handling & stacking all complete as per approved shop drawings & design mix as per the direction of the Engineer-in-charge. (Cost of strands should be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately) Extra for using M-60 (Cement content 440 kg) instead of M-40 150mm thick hollow core slab) is derived from 2 priced inputs and works out to ₹44.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail cost of 16.20 cum (120 Rmt )
  • 120 Rmt X 1.20 m X 0.15 (25 % hollow)
  • Cement for M-60 Mix = 7.128 T
  • Cement for M-40 Mix = 6.480 T
  • Difference 0.648 T
  • Plasticizer for M-60 Mix = 142.56 Kgs
  • Plasticizer for M-40 Mix = 129.600 Kgs
  • Difference 12.960 Kgs
ANALYSIS OF RATES · ITEM 26.73.3.3
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.6485,156.003,341.09
7318MATPlasticizer or Super Plasticizer 2% of cement contentPlasticizer / super plasticizerkg12.9630.00388.80
BUILD-UP TO RATE
TOTAL
3,729.89
Add 1 % Water charges on “W”
+37.30
TOTAL
3,767.19
Add GST on “X” (multiplying factor 0.2127)
+801.28
TOTAL
4,568.47
Add 15% CPOH on “Y”
+685.27
TOTAL
5,253.74
Add Cess @ 1% on “Z”
+52.54
Cost for 120 metre
5,306.28
Cost of 1 metre
44.22
SAY
₹44.20
D-02/SOURCEPRINTED PAGE 2009
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2009

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2009. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.