CPWD Analysis of Rates · New Technologies and Materials

Providing and fixing 50 mm thick extruded polystyrene rigid insulation board of required size between cavity wall, complying with ISO 4898:2008 & ASTM C 578-08b - type VI, having thermal conductivity of 0.0289 W/m K as per ASTM C 578 (measured as per IS 3346), compressive strength of > 350 kPa listed as per ASTM D 1621, density of 34-36 kg/m³ as per ASTM D 1622, water absorptions ≤ 1% by volume as per ASTM D 2842, oxygen index of 24.1 to 28.1 listed as per ASTM D 2863, cell size 0.4 mm of dia (max) as per ASTM D 3576. Fire retardent property as per DIN 4102, Part 1 of class B2 and as per ASTM E84 class A, fixed with suitable water based adhesive and fastener, complete in all respect as per the direction of Engineer-in-Charge

Item number
26.7
Analysis basis
Details of cost for 10 Sqm
Priced inputs
5
Derived rate
1,004.55 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.7 Providing and fixing 50 mm thick extruded polystyrene rigid insulation board of required size between cavity wall, complying with ISO 4898:2008 & ASTM C 578-08b - type VI, having thermal conductivity of 0.0289 W/m K as per ASTM C 578 (measured as per IS 3346), compressive strength of > 350 kPa listed as per ASTM D 1621, density of 34-36 kg/m³ as per ASTM D 1622, water absorptions ≤ 1% by volume as per ASTM D 2842, oxygen index of 24.1 to 28.1 listed as per ASTM D 2863, cell size 0.4 mm of dia (max) as per ASTM D 3576. Fire retardent property as per DIN 4102, Part 1 of class B2 and as per ASTM E84 class A, fixed with suitable water based adhesive and fastener, complete in all respect as per the direction of Engineer-in-Charge — is derived from 5 priced inputs for 10 Sqm and works out to ₹1,004.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • including 2% wastage
CodeInputUnitQuantityRate (INR)Amount (INR)
8561Extruded polystyrene rigid insulation board 50 mm thickMaterialsqm10.2610.006,222.00
0111Carpenter 1st classLabourday0.25897.00224.25
0128MateLabourday0.25816.00204.00
0114BeldarLabourday0.25736.00184.00
9999Sundries (Water based adhesive, fasteners, scaffolding etc.)MaterialL.S.1002.27227.00
TOTAL
7,061.25
Add 1 % Water charges on “W”
70.61
TOTAL
7,131.86
Add GST on “X” (multiplying factor 0.2127)
1,516.95
TOTAL
8,648.81
Add 15% CPOH on “Y”
1,297.32
TOTAL
9,946.13
Add Cess @ 1% on “Z”
99.46
Cost of 10 sqm
10,045.59
Cost of 1 sqm
1,004.56
Say
1,004.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1918. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.