Providing and fixing in position factory made non asbestos fibre reinforced aerated cement sandwich wall/roof/floor light weight solid core panels made of light weight cement concrete core composed of OPC cement, pulverized flyash, quick lime, cotton pulp & Gypsum in mortar state mixed with aeration agent in a preset mould. The outer face on both sides of the panels will be non asbestos fibre cement board conforming to IS 14862:2000. These solid wall panels are installed using Galvanized iron steel tracks/C channel of 1mm thick of required sizes as recommended by manufacturer’s and fixed to floor and RCC soffit in plumb to each other with steel screw/fasteners. The panel shall be fixed vertically with tongue & groove joint with cement based polymer modified jointing compound. The exposed surface finished with fibre mesh/glass fibre tape with polymer based jointing compound having superior flexibility. Panels should be used as floor & roofing with additional structural support, steel or RCC depending upon the design. All the operation shall be completed in all respect as per drawings, Manufacturers specifications and under the overall direction of Engineer-inCharge (Cost of all the material is included except “tracks/C channel” which will be paid separately)

Non load bearing panels 75 mm thick of required size (minimum 5mm thick fibre cement board Type B, Category III as per IS: 14862:2000 on both faces)
Item number
26.50.2
Analysis basis
Details of cost 10sqm (6.95Nos x0.6m
Priced inputs
5
Derived rate
₹1,841.20
D-01/RATE ANALYSISITEM 26.50.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.50.2 (Providing and fixing in position factory made non asbestos fibre reinforced aerated cement sandwich wall/roof/floor light weight solid core panels made of light weight cement concrete core composed of OPC cement, pulverized flyash, quick lime, cotton pulp & Gypsum in mortar state mixed with aeration agent in a preset mould. The outer face on both sides of the panels will be non asbestos fibre cement board conforming to IS 14862:2000. These solid wall panels are installed using Galvanized iron steel tracks/C channel of 1mm thick of required sizes as recommended by manufacturer’s and fixed to floor and RCC soffit in plumb to each other with steel screw/fasteners. The panel shall be fixed vertically with tongue & groove joint with cement based polymer modified jointing compound. The exposed surface finished with fibre mesh/glass fibre tape with polymer based jointing compound having superior flexibility. Panels should be used as floor & roofing with additional structural support, steel or RCC depending upon the design. All the operation shall be completed in all respect as per drawings, Manufacturers specifications and under the overall direction of Engineer-inCharge (Cost of all the material is included except “tracks/C channel” which will be paid separately) Non load bearing panels 75 mm thick of required size (minimum 5mm thick fibre cement board Type B, Category III as per IS: 14862:2000 on both faces)) is derived from 5 priced inputs and works out to ₹1,841.20 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • x2.40m = 10sqm)
  • Panel area = 10.00sqm, Add wastage @ 5%
  • = 0.50sqm, Total area = 10.50 sqm
  • For fixing, aligning, locking the panels, glass
  • fibre tape/fibre mesh with a jointing compound.
ANALYSIS OF RATES · ITEM 26.50.2DETAILS OF COST 10SQM (6.95NOS X0.6M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0245MATFactory made light weight non asbestos fibre reinforced aerated cement sandwitched wall/roof panel (75mm thick). The outer face on both sides of the panels will be non asbestos fibre cement board (minimum 5mm thick) Type B, Category III conforming to IS 14862:2000Factory made light weight non asbestos fibre reinforced aerated cement sandwitched wall/roof panel (75 mm thick). The outer face on both sides of the panels will be non asbestos fibre cement board (minimum 5 mm thick) Type B, Category III as per IS 14862:2000sqm10.5860.009,030.00
9999MATSundries, cement based polymer modified jointing compound, polymer based jointing compound having superior flexibility, fibre glass tape etcL.S.5002.271,135.00
0123LABMason 1st classMason 1st classday1897.00897.00
0114LABBeldarday2736.001,472.00
0131LABPainterday0.5816.00408.00
BUILD-UP TO RATE
TOTAL
12,942.00
Add 1 % Water charges on “W”
+129.42
TOTAL
13,071.42
Add GST on “X” (multiplying factor 0.2127)
+2,780.29
TOTAL
15,851.71
Add 15% CPOH on “Y”
+2,377.76
TOTAL
18,229.47
Add Cess @ 1% on “Z”
+182.29
Cost of 10 sqm
18,411.76
Cost of 1sqm
1,841.18
SAY
₹1,841.20
D-02/SOURCEPRINTED PAGE 1982
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1982

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1982. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.