Providing and laying SBR Polymer modified (of approved make @ minimum 2% by wt. of cement used) plain/reinforced concrete jacket for the structural members e.g. columns, pillars, piers, beams etc with concrete having the specified minimum characteristic compressive strength [with ordinary portland cement, coarse sand and graded stone aggregate of 10mm maximum size in proportion as per design criteria] with specified average thickness allround existing core of RCC member. Note: Rates shall be for finished surface area of concrete and shall include the cost of making holes in existing RCC slab, if required, for pouring concrete in shuttering mould of jacket and appropriate approved Super-Plasticiser for rendering concrete as flowable self compacting and SBR polymer but shall exclude cost of reinforcement, bond coat, Shear Keys, centering and shuttering, strutting, propping etc (Payment under this item shall be made only after proper wet curing has been done and surface has been satisfactorily evaluated by sounding/ tapping with a blunt metal instrument)
75mm thick in Grade M 25 with cement content not less than 330 kg per cum
- Item number
- 26.34.2
- Analysis basis
- Detail of cost for 10 sqm area (0.75cum)
- Priced inputs
- 3
- Derived rate
- ₹853.70 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.34.2 — Providing and laying SBR Polymer modified (of approved make @ minimum 2% by wt. of cement used) plain/reinforced concrete jacket for the structural members e.g. columns, pillars, piers, beams etc with concrete having the specified minimum characteristic compressive strength [with ordinary portland cement, coarse sand and graded stone aggregate of 10mm maximum size in proportion as per design criteria] with specified average thickness allround existing core of RCC member. Note: Rates shall be for finished surface area of concrete and shall include the cost of making holes in existing RCC slab, if required, for pouring concrete in shuttering mould of jacket and appropriate approved Super-Plasticiser for rendering concrete as flowable self compacting and SBR polymer but shall exclude cost of reinforcement, bond coat, Shear Keys, centering and shuttering, strutting, propping etc (Payment under this item shall be made only after proper wet curing has been done and surface has been satisfactorily evaluated by sounding/ tapping with a blunt metal instrument) 75mm thick in Grade M 25 with cement content not less than 330 kg per cum — is derived from 3 priced inputs for 10 sqm and works out to ₹853.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- M25 concrete 0.75 cum of concrete@ 330
- kg/cum
- Deduction of pumping charges
- @2% of cement 247.50 kg = 247.50X2% =
- 4.95 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item No.5.33.2.1 of SH: RCCRate as per item 5.33.2.1Sub-analysis | cum | 0.75 | 9,860.40 | 7,395.30 | |
| 0009 | Pumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinery | cum | -0.75 | 250.00 | -187.50 |
| 7914 | SBR PolymerMaterial | kg | 4.95 | 200.00 | 990.00 |
- TOTAL
- 8,197.80
- Add 1 % Water charges on “W-A”
- 8.02
- TOTAL
- 8,205.82
- Add GST on “X-A” (multiplying factor 0.2127)
- 172.40
- TOTAL
- 8,378.22
- Add 15% CPOH on “Y-A”
- 147.44
- TOTAL
- 8,525.66
- Add Cess @ 1% on “Z-A”
- 11.30
- Cost of 10 sqm
- 8,536.96
- Cost of 1 sqm
- 853.70
- Say
- 853.70
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1954. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.