Providing and fixing mineral fibre false ceiling tiles at all heights of size 595X595mm of approved texture, design and pattern. The tiles should have Humidity Resistance (RH) of 99%, Light Reflectance ≥ 85%, Thermal Conductivity k = 0.052 - 0.057 w/m K, Fire Performance as per (BS 476 pt - 6 &7)in true horizont al level suspended on interlocking T-Grid of hot dipped all round galvanized iron section of 0.33 mm thick (galvanized @120 gsm) comprising of main T runners of 15x32 mm of length 3000 mm, cross T of size 15x32mm of length 1200 mm and secondary intermediate cross T of size 15x32 mm of length 600 mm to form grid module of size 600x600 mm suspended from ceiling using galvanized mild steel item (galvanised@80gsm) 50 mm long 8mm outer diameter M-6 dash fasteners, 6 mm diameter fully threaded hanger rod up to 1000 mm length and L-shape level adjuster of size 85x25x2 mm, spaced at 1200 mm centre to centre along main ‘T’. The system should rest on periphery walls /partitions with the help of GI perimeter wall angle of size24x24X3000 mm made of 0.40 mm thick sheet, to be fixed to the wall with help of plastic rawl plug at 450 mm centre to centre & 40 mm long dry wall S.S. screws. The exposed bottom portion of all T-sections used in false ceiling support system shall be pre-painted with polyester baked paint, for all heights. The work shall be carried out as per specifications, drawings and as per directions of the engineer-in-charge

With 16 mm thick beveled tegular mineral fibre Anti-microbial false ceiling tile conforming to ISO 5 (class 100 ) specifications

Item number
26.27.3
Analysis basis
Details of cost for 100 Sqm
Priced inputs
13
Derived rate
2,447.15 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.27.3 Providing and fixing mineral fibre false ceiling tiles at all heights of size 595X595mm of approved texture, design and pattern. The tiles should have Humidity Resistance (RH) of 99%, Light Reflectance ≥ 85%, Thermal Conductivity k = 0.052 - 0.057 w/m K, Fire Performance as per (BS 476 pt - 6 &7)in true horizont al level suspended on interlocking T-Grid of hot dipped all round galvanized iron section of 0.33 mm thick (galvanized @120 gsm) comprising of main T runners of 15x32 mm of length 3000 mm, cross T of size 15x32mm of length 1200 mm and secondary intermediate cross T of size 15x32 mm of length 600 mm to form grid module of size 600x600 mm suspended from ceiling using galvanized mild steel item (galvanised@80gsm) 50 mm long 8mm outer diameter M-6 dash fasteners, 6 mm diameter fully threaded hanger rod up to 1000 mm length and L-shape level adjuster of size 85x25x2 mm, spaced at 1200 mm centre to centre along main ‘T’. The system should rest on periphery walls /partitions with the help of GI perimeter wall angle of size24x24X3000 mm made of 0.40 mm thick sheet, to be fixed to the wall with help of plastic rawl plug at 450 mm centre to centre & 40 mm long dry wall S.S. screws. The exposed bottom portion of all T-sections used in false ceiling support system shall be pre-painted with polyester baked paint, for all heights. The work shall be carried out as per specifications, drawings and as per directions of the engineer-in-charge With 16 mm thick beveled tegular mineral fibre Anti-microbial false ceiling tile conforming to ISO 5 (class 100 ) specifications — is derived from 13 priced inputs for 100 Sqm and works out to ₹2,447.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Area = 100 sqm + 5 sqm (Add for wastage
  • @5%) Total = 105 sqm
  • including 10 % wastage
  • including 10 % wastage
  • including 10 % wastage
  • including 10 % wastage
CodeInputUnitQuantityRate (INR)Amount (INR)
8553Mineral fibre beveled tegular edged ceiling tiles 595x595 mm, 16 mm thick with bioblock, conforming to ISO 5 (class 100) specificationsMineral fibre beveled tegular edged ceiling tiles 595 x595 mm,16 mm thick with bio-block conforming to ISO 5 (class 100) specifications.Materialsqm1051,020.001,07,100.00
8555G.I. main runner 15X32mm of 3000 mm length, 0.33mm thickG.I main runner 15 x32 mm of 3000 mm length, 0.33 mm thickMaterialeach29.5142.004,189.00
8556G.I. cross Tee 15X32mm of 1200mm length 0.33mm thickG.I cross-T 15 x32 mm of 1200 mm length, 0.33 mm thickMaterialeach14757.008,379.00
8557G.I. cross Tee 15X32mm of 600mm length,0.33 mm thickG.I cross-T 15 x32 mm of 600 mm length, 0.33 mm thickMaterialeach14729.004,263.00
8591Galvanised Steel perimeter wall Angle Size 24 x 24 x 0.40 mm (3.00 metre long)Materialeach13.5114.001,539.00
8558Galvanised Iron hanger rod 6mm dia fully threaded upto 1000mm lengthG.I hanger rod 6 mm dia fully threaded upto 1000 mm lengthMaterialeach7217.001,224.00
8619Galavanised MS L-shape level adjuster of size 85x25x2 mmGalavanised MS L-shape level adjuster of size 85x25x2 mmMaterialeach7218.001,296.00
8596Galavanised MS 8 mm outer diameter M-6 dash fastener 50mm longGalvanised MS 8 mm outer diameter M-6 dash fastener 25 mm longMaterialeach7215.001,080.00
821140 mm long S.S screws with plastic rawl plugsStainless steel screws 40 mmMaterial100 nos1270.00270.00
9999Sundries i.e. scaffolding etcMaterialL.S.187.952.27426.65
9977Carriage of material etc.MaterialL.S.89.352.27202.82
0111Carpenter 1st classLabourday28897.0025,116.00
0114BeldarLabourday23736.0016,928.00
TOTAL
1,72,013.47
Add 1 % Water charges on “W”
1,720.13
TOTAL
1,73,733.60
Add GST on “X” (multiplying factor 0.2127)
36,953.14
TOTAL
2,10,686.74
Add 15% CPOH on “Y”
31,603.01
TOTAL
2,42,289.75
Add Cess @ 1% on “Z”
2,422.90
Cost of 100 sqm
2,44,712.65
Cost of 1 sqm
2,447.13
Say
2,447.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1945. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.