CPWD Analysis of Rates · New Technologies and Materials
Providing & fixing false ceiling at all heights with GRG (Glass Fibre Reinforced Gypsum) false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having moisture content less than 2%, humidity resistance of 99%, NRC0.50 to 0.75 as per IS 8225:1987, Non combustible as per BS 476 (part 4)-1970 and light reflectance of 85% (minimum) to be laid in true horizontal level suspended on inter-locking metal T-Grid of hot dipped galvanised iron section of 0.33mm thick (galvanized @ 120 grams per sqm including both sides) comprising of main-T runners of size 15x32 mm of length 3000 mm, cross - T of size 15x32 mm of length 1200 mm and secondary intermediate cross-T of size 15x32 mm of length 600mm to form grid module of size 600 x 600 mm, suspended from ceiling using galvanised mild steel items (galvanizing @ 80 grams per sqm) i.e. 50 mm long, 8 mm outer diameter M-6 dash fasteners, 6 mm dia fully threaded hanger rod upto 1000 mm length and L-shape level adjuster of size 85x25x2 mm. Galvanised iron perimeter wall angle of size 24x24x0.40 mm of length 3000 mm to be fixed on periphery wall / partition with the help of plastic rawl plugs at 450 mm center to center and 40 mm long dry wall wood screws. The work shall be carried out as per specifications, drawing and as per directions of the Engineer-in-Charge
With fully perforated 12 mm thick micro tegular edged or 10 mm thick square edged GRG false ceiling tiles
- Item number
- 26.26.2
- Analysis basis
- Details of cost for 100 sqm
- Priced inputs
- 14
- Derived rate
- ₹1,907.35 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.26.2 — Providing & fixing false ceiling at all heights with GRG (Glass Fibre Reinforced Gypsum) false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having moisture content less than 2%, humidity resistance of 99%, NRC0.50 to 0.75 as per IS 8225:1987, Non combustible as per BS 476 (part 4)-1970 and light reflectance of 85% (minimum) to be laid in true horizontal level suspended on inter-locking metal T-Grid of hot dipped galvanised iron section of 0.33mm thick (galvanized @ 120 grams per sqm including both sides) comprising of main-T runners of size 15x32 mm of length 3000 mm, cross - T of size 15x32 mm of length 1200 mm and secondary intermediate cross-T of size 15x32 mm of length 600mm to form grid module of size 600 x 600 mm, suspended from ceiling using galvanised mild steel items (galvanizing @ 80 grams per sqm) i.e. 50 mm long, 8 mm outer diameter M-6 dash fasteners, 6 mm dia fully threaded hanger rod upto 1000 mm length and L-shape level adjuster of size 85x25x2 mm. Galvanised iron perimeter wall angle of size 24x24x0.40 mm of length 3000 mm to be fixed on periphery wall / partition with the help of plastic rawl plugs at 450 mm center to center and 40 mm long dry wall wood screws. The work shall be carried out as per specifications, drawing and as per directions of the Engineer-in-Charge With fully perforated 12 mm thick micro tegular edged or 10 mm thick square edged GRG false ceiling tiles — is derived from 14 priced inputs for 100 sqm and works out to ₹1,907.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Celling area =100 sqm
- Total=105.00 sqm
- Including wastage @ 10%
- Including wastage @ 10%
- Including wastage @ 10%
- Including wastage @ 10%
- Add wastage @ 5% = 5 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8582 | 12 mm thick micro tegular edged fully perforated GFRG (Glass Fibre Reinforced Gypsum) false celing tiles of Size 595x595 mm12 mm thick micro tegular edged fully perforated GRG (Glass Fibre Reinforced Gypsum) false celing tiles of size 595x595 mmMaterial | sqm | 105 | 642.00 | 67,410.00 |
| 8555 | Galvanized iron main-T ceiling sections 15x32x0.33 mm (3000 mm long)G.I main runner 15 x32 mm of 3000 mm length, 0.33 mm thickMaterial | each | 29.5 | 142.00 | 4,189.00 |
| 8591 | Galvanized iron perimeter wall angle 24x24x0.40 mm (3000 mm long)Galvanised Steel perimeter wall Angle size 24 x 24 x 0.40 mm (3.00 metre long)Material | each | 13.5 | 114.00 | 1,539.00 |
| 8556 | Galvanized iron intermediate crossT section 15x32x0.33 mm (1200 mm long)G.I cross-T 15 x32 mm of 1200 mm length, 0.33 mm thickMaterial | each | 147 | 57.00 | 8,379.00 |
| 8557 | Galvanized iron intermediate cross-T section 15x32x0.33 mm (600 mm long)G.I cross-T 15 x32 mm of 600 mm length, 0.33 mm thickMaterial | each | 147 | 29.00 | 4,263.00 |
| 8588 | Galavanised MS hanger rod 6mm dia MS fully threaded up to 1000 mm lengthGalavanised MS hanger rod 6 mm dia MS fully threaded up to 1000 mm lengthMaterial | each | 72 | 17.00 | 1,224.00 |
| 8619 | Galavanised MS L-shape level adjuster of size 85x25x2 mmGalavanised MS L-shape level adjuster of size 85x25x2 mmMaterial | each | 72 | 18.00 | 1,296.00 |
| 8596 | Galvanised MS 8mm outer diameter M-6 dash fastener 25mm longGalvanised MS 8 mm outer diameter M-6 dash fastener 25 mm longMaterial | each | 72 | 15.00 | 1,080.00 |
| 8211 | 40mm long SS screws with plastic rawl plugsStainless steel screws 40 mmMaterial | 100 nos | 1 | 270.00 | 270.00 |
| 9999 | Scaffolding etc.Material | L.S. | 498.65 | 2.27 | 1,131.94 |
| 9977 | Carriage of materials etc.Material | L.S. | 237.48 | 2.27 | 539.08 |
| 9999 | SundriesMaterial | L.S. | 310.7 | 2.27 | 705.29 |
| 0111 | Carpenter 1st classLabour | day | 28 | 897.00 | 25,116.00 |
| 0114 | BeldarLabour | day | 23 | 736.00 | 16,928.00 |
- TOTAL
- 1,34,070.31
- Add 1 % Water charges on “W”
- 1,340.70
- TOTAL
- 1,35,411.01
- Add GST on “X” (multiplying factor 0.2127)
- 28,801.92
- TOTAL
- 1,64,212.93
- Add 15% CPOH on “Y”
- 24,631.94
- TOTAL
- 1,88,844.87
- Add Cess @ 1% on “Z”
- 1,888.45
- Cost of 100 sqm
- 1,90,733.32
- Cost of 1 sqm
- 1,907.33
- Say
- 1,907.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1942. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.