Providing and fixing 15 mm thick false ceiling tiles at all heights with integral densified calcium silicate reinforced with fibre and natural filler false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having NRC (Noise Reduction coefficient) of 0.50 (minimum) as per IS 8225:1987, Light reflectance of 85% (minimum). Non combustible as per BS:476 (part-4), fire performance as per BS:476 (part 6 &7), humidity resistance of 100%, thermal conductivity < 0.043 W/m K as per ASTM 518:1991,in true horizontal level on the existing frame work consisting of T-sections and Lsections suitably fixed according to tile size as per direction of Engineer-in-charge
- Item number
- 26.25
- Analysis basis
- 10 Sqm
- Priced inputs
- 6
- Derived rate
- ₹1,781.20/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.25 (Providing and fixing 15 mm thick false ceiling tiles at all heights with integral densified calcium silicate reinforced with fibre and natural filler false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having NRC (Noise Reduction coefficient) of 0.50 (minimum) as per IS 8225:1987, Light reflectance of 85% (minimum). Non combustible as per BS:476 (part-4), fire performance as per BS:476 (part 6 &7), humidity resistance of 100%, thermal conductivity < 0.043 W/m K as per ASTM 518:1991,in true horizontal level on the existing frame work consisting of T-sections and Lsections suitably fixed according to tile size as per direction of Engineer-in-charge) is derived from 6 priced inputs for 10 Sqm and works out to ₹1,781.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 10 + 0.5 (Add wastage @5%) = 10.5 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8589 | MAT | Calcium Silicate tegular edged celling tiles 595x595 mm and 15 mm thickCalcium Silicate tegular edged celling tiles 595x595 mm and 15 mm thick on edges | sqm | 10.5 | 822.00 | 8,631.00 |
| 9977 | MAT | Carriage | L.S. | 14.95 | 2.27 | 33.94 |
| 0111 | LAB | Carpenter 1st class | day | 2.5 | 897.00 | 2,242.50 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
| 9999 | MAT | Scaffolding | L.S. | 31.07 | 2.27 | 70.53 |
| 9999 | MAT | Sundries | L.S. | 31.07 | 2.27 | 70.53 |
- TOTAL
- 12,520.50
- Add 1 % Water charges on “W”
- +125.21
- TOTAL
- 12,645.71
- Add GST on “X” (multiplying factor 0.2127)
- +2,689.74
- TOTAL
- 15,335.45
- Add 15% CPOH on “Y”
- +2,300.32
- TOTAL
- 17,635.77
- Add Cess @ 1% on “Z”
- +176.36
- Cost of 10 sqm
- 17,812.13
- Cost of 1 sqm
- 1,781.21
- SAY
- ₹1,781.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1940
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1940. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.