CPWD Analysis of Rates · New Technologies and Materials
Providing and fixing 15 mm thick false ceiling tiles at all heights with integral densified calcium silicate reinforced with fibre and natural filler false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having NRC (Noise Reduction coefficient) of 0.50 (minimum) as per IS 8225:1987, Light reflectance of 85% (minimum). Non combustible as per BS:476 (part-4), fire performance as per BS:476 (part 6 &7), humidity resistance of 100%, thermal conductivity < 0.043 W/m K as per ASTM 518:1991,in true horizontal level on the existing frame work consisting of T-sections and Lsections suitably fixed according to tile size as per direction of Engineer-in-charge
- Item number
- 26.25
- Analysis basis
- Details of cost for 10 Sqm
- Priced inputs
- 6
- Derived rate
- ₹1,781.20 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.25 — Providing and fixing 15 mm thick false ceiling tiles at all heights with integral densified calcium silicate reinforced with fibre and natural filler false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having NRC (Noise Reduction coefficient) of 0.50 (minimum) as per IS 8225:1987, Light reflectance of 85% (minimum). Non combustible as per BS:476 (part-4), fire performance as per BS:476 (part 6 &7), humidity resistance of 100%, thermal conductivity < 0.043 W/m K as per ASTM 518:1991,in true horizontal level on the existing frame work consisting of T-sections and Lsections suitably fixed according to tile size as per direction of Engineer-in-charge — is derived from 6 priced inputs for 10 Sqm and works out to ₹1,781.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 10 + 0.5 (Add wastage @5%) = 10.5 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8589 | Calcium Silicate tegular edged celling tiles 595x595 mm and 15 mm thickCalcium Silicate tegular edged celling tiles 595x595 mm and 15 mm thick on edgesMaterial | sqm | 10.5 | 822.00 | 8,631.00 |
| 9977 | CarriageMaterial | L.S. | 14.95 | 2.27 | 33.94 |
| 0111 | Carpenter 1st classLabour | day | 2.5 | 897.00 | 2,242.50 |
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 9999 | ScaffoldingMaterial | L.S. | 31.07 | 2.27 | 70.53 |
| 9999 | SundriesMaterial | L.S. | 31.07 | 2.27 | 70.53 |
- TOTAL
- 12,520.50
- Add 1 % Water charges on “W”
- 125.21
- TOTAL
- 12,645.71
- Add GST on “X” (multiplying factor 0.2127)
- 2,689.74
- TOTAL
- 15,335.45
- Add 15% CPOH on “Y”
- 2,300.32
- TOTAL
- 17,635.77
- Add Cess @ 1% on “Z”
- 176.36
- Cost of 10 sqm
- 17,812.13
- Cost of 1 sqm
- 1,781.21
- Say
- 1,781.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1940. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works