Providing and fixing false ceiling at all heights with integral densified calcium silicate reinforced with fibre and natural filler false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having NRC (Noise Reduction coefficient) of 0.50 (minimum) as per IS 8225:1987, Light reflectance of 85% (minimum). Non combustible as per BS:476 (part-4), fire performance as per BS:476 (part 6 &7), humidity resistance of 100%, thermal conductivity < 0.043 W/m K as per ASTM 518:1991, in true horizontal level suspended on inter-locking metal powder coated T-Grid of hot dipped galvanised iron section of 0.40 mm thick on Silhouette profile,rotary stiched double webbed white with 6mm reveal profile (white/ black),comprising of main-T runners of size 15x42mm of length 3000 mm, cross - T of size 15x42 mm of length 1200 mm and secondary intermediate cross-T of size 15x42 mm of length 600mm to form grid module of size 600 x 600 mm, suspended from ceiling using galvanised mild steel items (galvanizing @ 80 grams per sqm) i.e. 50 mm long, 8 mm outer diameter M-6 dash fasteners, 6 mm dia fully threaded hanger rod upto 1000 mm length and L-shape level adjuster of size 85x25x2 mm. Galvanised iron perimeter wall angle of size 22x19x0.40 mm of length 3000 mm to be fixed on periphery wall / partition with the help of plastic rawl plugs at 450 mm center to center and 40mm long dry wall S.S screws. The work shall be carried out as per specifications, drawing and as per directions of the Engineer-in-Charge
With 15 mm thick integral densified micro edge light weight calcium silicate false ceiling tiles
- Item number
- 26.23.1
- Analysis basis
- Details of cost for 100 sqm
- Priced inputs
- 14
- Derived rate
- ₹2,630.40 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.23.1 — Providing and fixing false ceiling at all heights with integral densified calcium silicate reinforced with fibre and natural filler false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having NRC (Noise Reduction coefficient) of 0.50 (minimum) as per IS 8225:1987, Light reflectance of 85% (minimum). Non combustible as per BS:476 (part-4), fire performance as per BS:476 (part 6 &7), humidity resistance of 100%, thermal conductivity < 0.043 W/m K as per ASTM 518:1991, in true horizontal level suspended on inter-locking metal powder coated T-Grid of hot dipped galvanised iron section of 0.40 mm thick on Silhouette profile,rotary stiched double webbed white with 6mm reveal profile (white/ black),comprising of main-T runners of size 15x42mm of length 3000 mm, cross - T of size 15x42 mm of length 1200 mm and secondary intermediate cross-T of size 15x42 mm of length 600mm to form grid module of size 600 x 600 mm, suspended from ceiling using galvanised mild steel items (galvanizing @ 80 grams per sqm) i.e. 50 mm long, 8 mm outer diameter M-6 dash fasteners, 6 mm dia fully threaded hanger rod upto 1000 mm length and L-shape level adjuster of size 85x25x2 mm. Galvanised iron perimeter wall angle of size 22x19x0.40 mm of length 3000 mm to be fixed on periphery wall / partition with the help of plastic rawl plugs at 450 mm center to center and 40mm long dry wall S.S screws. The work shall be carried out as per specifications, drawing and as per directions of the Engineer-in-Charge With 15 mm thick integral densified micro edge light weight calcium silicate false ceiling tiles — is derived from 14 priced inputs for 100 sqm and works out to ₹2,630.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Celling Area = 100 sqm + Add 5% wastage
- = 5 sqm. Total = 105 sqm
- SILHOUETTE Profile grid frame :
- including wastage @10%
- including wastage @10%
- including wastage @10%
- including wastage @10%
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8563 | 15 mm thick, light weight, integral densified micro look edged,false ceiling tiles of size 595x595 mm15 mm thick, light weight, integral densified micro look edged,false ceiling tiles of size 595x595 mm.Material | sqm | 105 | 925.00 | 97,125.00 |
| 8567 | Galvanized mild steel perimeter wall angle 22x19x0.40 mm (3000 mm long)Material | each | 13.5 | 131.00 | 1,768.50 |
| 8566 | Powder coated steel section main-T ceiling sections 15x42x0.40 mm (3000 mm long)Material | each | 29.5 | 296.00 | 8,732.00 |
| 8568 | Powder coated Galvanised Iron intermediate cross-T section 15x42x0.40 mm (1200 mm long)Material | each | 147 | 120.00 | 17,640.00 |
| 8569 | Powder coated Galvanized Iron intermediate cross-T section 15x42x0.40mm (600 mm long )Powder coated Galvanized Iron intermediate cross-T section 15x42x0.40 mm (600 mm long )Material | each | 147 | 60.00 | 8,820.00 |
| 8588 | Galavanised MS hanger rod 6 mm dia MS fully threaded up to 1000 mm lengthMaterial | each | 72 | 17.00 | 1,224.00 |
| 8619 | Galavanised MS L-shape level adjuster of size 85x25x2 mmGalavanised MS L-shape level adjuster of size 85x25x2 mmMaterial | each | 72 | 18.00 | 1,296.00 |
| 8515 | Galavanised MS 8 mm outer diameter M-6 dash fastener 50mm longGalavanised MS 8 mm outer diameter M-6 dash fastener 50 mm longMaterial | each | 72 | 50.00 | 3,600.00 |
| 8211 | 40 mm long S.S screws with plastic rawl plugsStainless steel screws 40 mmMaterial | 100 nos | 1 | 270.00 | 270.00 |
| 9999 | Scaffolding etc.Material | L.S. | 498.65 | 2.27 | 1,131.94 |
| 9977 | Carriage of materials etc.Material | L.S. | 237.48 | 2.27 | 539.08 |
| 9999 | SundriesMaterial | L.S. | 310.7 | 2.27 | 705.29 |
| 0111 | Carpenter 1st classLabour | day | 28 | 897.00 | 25,116.00 |
| 0114 | BeldarLabour | day | 23 | 736.00 | 16,928.00 |
- TOTAL
- 1,84,895.81
- Add 1 % Water charges on “W”
- 1,848.96
- TOTAL
- 1,86,744.77
- Add GST on “X” (multiplying factor 0.2127)
- 39,720.61
- TOTAL
- 2,26,465.38
- Add 15% CPOH on “Y”
- 33,969.81
- TOTAL
- 2,60,435.19
- Add Cess @ 1% on “Z”
- 2,604.35
- Cost of 100 sqm.
- 2,63,039.54
- Cost of 1 sqm.
- 2,630.40
- Say
- 2,630.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1938. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works