Supplying and laying high strength flexible geogrids (HSFG) as soil reinforcement / basal reinforcement as per MORTH 3100 and IRC 113, made of high tenacity polyester core with polyethylene coating with Minimum Long Term Design Strength (LTDS) of more than 50% of ultimate tensile strength at 30 degree Celcius corresponding to 12 % strain

Ultimate tensile strength350 kN/m
Item number
26.18.6
Analysis basis
300 Sqm
Priced inputs
4
Derived rate
₹699.05/ SQM
D-01/RATE ANALYSISITEM 26.18.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.18.6 (Supplying and laying high strength flexible geogrids (HSFG) as soil reinforcement / basal reinforcement as per MORTH 3100 and IRC 113, made of high tenacity polyester core with polyethylene coating with Minimum Long Term Design Strength (LTDS) of more than 50% of ultimate tensile strength at 30 degree Celcius corresponding to 12 % strain Ultimate tensile strength350 kN/m) is derived from 4 priced inputs for 300 Sqm and works out to ₹699.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • elements (synthetic geogrids) for wastage
  • and accessories like tie-strips, nuts and
  • bolts and loops/lugs for joining reinforcing
  • elements with the facia pannels, overlaps
  • and other protective elements for synthetic
  • geogrids and all other activities required to
  • complete the item in all respect including
  • Add 10 per cent of the cost of reinforcing
ANALYSIS OF RATES · ITEM 26.18.6DETAILS OF COST FOR 300 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8967MATSynthetic Geogrid having umtimate tensile strength 350 kN/mSynthetic Geogrid Ultimate tensile strength- 350kN/msqm300425.001,27,500.00
0128LABMateday0.36816.00293.76
0114LABBeldarday6736.004,416.00
0139LABSkilled BeldarSkilled Beldar (for floor rubbing etc.)day3816.002,448.00
BUILD-UP TO RATE
taxes and transportation. 10% of “P”
+12,750.00
TOTAL
1,47,407.76
Add 1 % Water charges on “W”
+1,474.08
TOTAL
1,48,881.84
Add GST on “X” (multiplying factor 0.2127)
+31,667.17
TOTAL
1,80,549.01
Add 15% CPOH on “Y”
+27,082.35
TOTAL
2,07,631.36
Add Cess @ 1% on “Z”
+2,076.31
Cost for 300 Sqm
2,09,707.67
Cost per Sqm
699.03
SAY
₹699.05
D-02/SOURCEPRINTED PAGE 1928
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1928

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1928. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.