Supplying and laying high strength flexible geogrids (HSFG) as soil reinforcement / basal reinforcement as per MORTH 3100 and IRC 113, made of high tenacity polyester core with polyethylene coating with Minimum Long Term Design Strength (LTDS) of more than 50% of ultimate tensile strength at 30 degree Celcius corresponding to 12 % strain

Ultimate tensile strength200 kN/m
Item number
26.18.3
Analysis basis
300 Sqm
Priced inputs
4
Derived rate
₹645.80/ SQM
D-01/RATE ANALYSISITEM 26.18.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.18.3 (Supplying and laying high strength flexible geogrids (HSFG) as soil reinforcement / basal reinforcement as per MORTH 3100 and IRC 113, made of high tenacity polyester core with polyethylene coating with Minimum Long Term Design Strength (LTDS) of more than 50% of ultimate tensile strength at 30 degree Celcius corresponding to 12 % strain Ultimate tensile strength200 kN/m) is derived from 4 priced inputs for 300 Sqm and works out to ₹645.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • elements (synthetic geogrids) for wastage
  • and accessories like tie-strips, nuts and
  • bolts and loops/lugs for joining reinforcing
  • elements with the facia pannels, overlaps
  • and other protective elements for synthetic
  • geogrids and all other activities required to
  • complete the item in all respect including
  • Add 10 per cent of the cost of reinforcing
ANALYSIS OF RATES · ITEM 26.18.3DETAILS OF COST FOR 300 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8964MATSynthetic Geogrid having umtimate tensile strength 200 kN/mSynthetic Geogrid Ultimate tensile strength- 200 kN/msqm300391.001,17,300.00
0128LABMateday0.36816.00293.76
0114LABBeldarday6736.004,416.00
0139LABSkilled BeldarSkilled Beldar (for floor rubbing etc.)day3816.002,448.00
BUILD-UP TO RATE
taxes and transportation. 10% of “P”
+11,730.00
TOTAL
1,36,187.76
Add 1 % Water charges on “W”
+1,361.88
TOTAL
1,37,549.64
Add GST on “X” (multiplying factor 0.2127)
+29,256.81
TOTAL
1,66,806.45
Add 15% CPOH on “Y”
+25,020.97
TOTAL
1,91,827.42
Add Cess @ 1% on “Z”
+1,918.27
Cost for 300 Sqm
1,93,745.69
Cost per Sqm
645.82
SAY
₹645.80
D-02/SOURCEPRINTED PAGE 1926
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1926

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1926. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.