CPWD Analysis of Rates · New Technologies and Materials

Supplying and laying high strength flexible geogrids (HSFG) as soil reinforcement / basal reinforcement as per MORTH 3100 and IRC 113, made of high tenacity polyester core with polyethylene coating with Minimum Long Term Design Strength (LTDS) of more than 50% of ultimate tensile strength at 30 degree Celcius corresponding to 12 % strain

Ultimate tensile strength1000 kN/m

Item number
26.18.13
Analysis basis
Details of Cost for 300 Sqm
Priced inputs
4
Derived rate
1,742.80 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.18.13 Supplying and laying high strength flexible geogrids (HSFG) as soil reinforcement / basal reinforcement as per MORTH 3100 and IRC 113, made of high tenacity polyester core with polyethylene coating with Minimum Long Term Design Strength (LTDS) of more than 50% of ultimate tensile strength at 30 degree Celcius corresponding to 12 % strain Ultimate tensile strength1000 kN/m — is derived from 4 priced inputs for 300 Sqm and works out to ₹1,742.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • elements (synthetic geogrids) for wastage
  • and accessories like tie-strips, nuts and
  • bolts and loops/lugs for joining reinforcing
  • elements with the facia pannels, overlaps
  • and other protective elements for synthetic
  • geogrids and all other activities required to
  • complete the item in all respect including
  • Add 10 per cent of the cost of reinforcing
CodeInputUnitQuantityRate (INR)Amount (INR)
8974Synthetic Geogrid having umtimate tensile strength 1000 kN/mSynthetic Geogrid Ultimate tensile strength- 1000kN/mMaterialsqm3001,092.003,27,600.00
0128MateLabourday0.36816.00293.76
0114BeldarLabourday6736.004,416.00
0139Skilled BeldarSkilled Beldar (for floor rubbing etc.)Labourday3816.002,448.00
taxes and transportation. 10% of “P”
32,760.00
TOTAL
3,67,517.76
Add 1 % Water charges on “W”
3,675.18
TOTAL
3,71,192.94
Add GST on “X” (multiplying factor 0.2127)
78,952.74
TOTAL
4,50,145.68
Add 15% CPOH on “Y”
67,521.85
TOTAL
5,17,667.53
Add Cess @ 1% on “Z”
5,176.68
Cost for 300 Sqm
5,22,844.21
Cost per Sqm
1,742.81
say
1,742.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1932. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.