Skip to main content
R/DAR 2023

Cement mortar 1:5 (1 cement : 5 fine sand)

Item number
3.5
Analysis basis
1 cum
Priced inputs
6
Derived rate
₹3,347.85/ CUM
D-01/RATE ANALYSISITEM 3.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 3.5 (Cement mortar 1:5 (1 cement : 5 fine sand)) is derived from 6 priced inputs for 1 cum and works out to ₹3,347.85 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (0.214 cum. of cement = 0.31 tonne) Cement required for cement mortar is 21.40%
ANALYSIS OF RATES · ITEM 3.5DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.315,156.001,598.36
0983MATFine sand (zone IV)cum1.07980.001,048.60
0114LABBeldarday0.75736.00552.00
0101LABBhistiday0.07816.0057.12
9999MATHire and running charges of mechanical mixerL.S.26.912.2761.09
9999MATSundriesL.S.13.522.2730.69
BUILD-UP TO RATE
Cost of 1.00 cum
3,347.86
SAY
₹3,347.85
D-02/SOURCEPRINTED PAGE 144
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
144

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 144. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSMORTARS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.