Analysis basis
Details of cost for 1 cum
Priced inputs
6
Derived rate
5,138.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 3.2 Cement mortar 1:2 (1 cement : 2 fine sand) — is derived from 6 priced inputs for 1 cum and works out to ₹5,138.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • (0.475 cum. of cement = 0.68 tonne) Cement required for cement mortar is 47.50%
CodeInputUnitQuantityRate (INR)Amount (INR)
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.685,156.003,506.08
0983Fine sand (zone IV)Materialcum0.95980.00931.00
0114BeldarLabourday0.75736.00552.00
0101BhistiLabourday0.07816.0057.12
9999Hire and running charges of mechanical mixerMaterialL.S.26.912.2761.09
9999SundriesMaterialL.S.13.522.2730.69
Cost of 1.00 cum
5,137.98
Say
5,138.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 143. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.