CPWD Analysis of Rates · Masonry Work
Brick work with clay flyash F.P.S. (non modular) brick of class designation 7.5 in superstructure above plinth level up to floor five level in
Cement mortar 1:4 (1 cement : 4 coarse sand)
- Item number
- 6.32.1
- Analysis basis
- Details of cost for 1 cum.
- Priced inputs
- 9
- Derived rate
- ₹9,333.45 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.32.1 — Brick work with clay flyash F.P.S. (non modular) brick of class designation 7.5 in superstructure above plinth level up to floor five level in : Cement mortar 1:4 (1 cement : 4 coarse sand) — is derived from 9 priced inputs for 1 cum and works out to ₹9,333.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
- Extra labour element required for lifting of
- materials above floor two level upto floor
- V level (0.75 x 1.5 = 1.13)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7008 | F.P.S.(non modular) clay fly ash bricks class designation 7.5F.P.S. (non modular) clay fly ash bricks class designation 7.5Material | 1000 Nos | 0.494 | 4,770.00 | 2,356.38 |
| Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysis | cum | 0.25 | 4,211.70 | 1,052.93 | |
| 9999 | SundriesMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.47 | 897.00 | 421.59 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.47 | 816.00 | 383.52 |
| 0115 | CoolieLabour | day | 1.8 | 736.00 | 1,324.80 |
| 0101 | BhistiLabour | day | 0.2 | 816.00 | 163.20 |
| 9999 | ScaffoldingMaterial | L.S. | 8.97 | 2.27 | 20.36 |
| 0115 | CoolieLabour | day | 1.13 | 736.00 | 831.68 |
- TOTAL
- 6,560.66
- Add 1 % Water charges on “W”
- 65.61
- TOTAL
- 6,626.27
- Add GST on “X” (multiplying factor 0.2127)
- 1,409.41
- TOTAL
- 8,035.68
- Add 15% CPOH on “Y”
- 1,205.35
- TOTAL
- 9,241.03
- Add Cess @ 1% on “Z”
- 92.41
- Cost per cum.
- 9,333.44
- Say
- 9,333.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 332. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.