CPWD Analysis of Rates · Masonry Work

Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand)

With Modular bricks

Item number
6.3.2
Analysis basis
Details of cost for 1 cum
Priced inputs
9
Derived rate
8,942.35 / Cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.3.2 Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) : With Modular bricks — is derived from 9 priced inputs for 1 cum and works out to ₹8,942.35 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Extra labour element required for lifting of
  • materials (above floor two level upto floor
  • five level)
CodeInputUnitQuantityRate (INR)Amount (INR)
7902Machine moulded common burnt clay modular perforated bricks of class designation 12.5Material1000 Nos0.4875,500.002,678.50
Rate as per item No 3.11 of SH: MortarRate as per item 3.11Sub-analysiscum0.223,541.40779.11
9999SundriesMaterialL.S.2.732.276.20
0123Mason 1st classMason 1st classLabourday0.44897.00394.68
0124Mason 2nd classMason 2nd classLabourday0.44816.00359.04
0115CoolieLabourday1.43736.001,052.48
0101BhistiLabourday0.18816.00146.88
9999ScaffoldingMaterialL.S.16.382.2737.18
0115CoolieLabourday1.13736.00831.68
TOTAL
6,285.75
Add 1 % Water charges on “W”
62.86
TOTAL
6,348.61
Add GST on “X” (multiplying factor 0.2127)
1,350.35
TOTAL
7,698.96
Add 15% CPOH on “Y”
1,154.84
TOTAL
8,853.80
Add Cess @ 1% on “Z”
88.54
Cost of 1 Cum.
8,942.34
Say
8,942.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 309. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works