CPWD Analysis of Rates · Masonry Work
Brick work with common burnt clay modular bricks of class designation 7.5 in exposed brick work including making horizontal and vertical grooves 10mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand)
Above plinth level upto floor V level
- Item number
- 6.27.2
- Analysis basis
- Details of cost for 1 cum.
- Priced inputs
- 9
- Derived rate
- ₹8,312.90 / Cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.27.2 — Brick work with common burnt clay modular bricks of class designation 7.5 in exposed brick work including making horizontal and vertical grooves 10mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand) Above plinth level upto floor V level — is derived from 9 priced inputs for 1 cum and works out to ₹8,312.90 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Extra labour for lifting of material (above
- floor two level up to floor five level)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7900 | Modular common burnt clay bricks of class designation 7.5Material | 1000 Nos | 0.487 | 4,500.00 | 2,191.50 |
| Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11Sub-analysis | cum | 0.22 | 3,541.40 | 779.11 | |
| 9999 | Sundries i/c steel / wooden strips for making groovesMaterial | L.S. | 16.38 | 2.27 | 37.18 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.44 | 897.00 | 394.68 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.44 | 816.00 | 359.04 |
| 0115 | CoolieLabour | day | 1.43 | 736.00 | 1,052.48 |
| 0101 | BhistiLabour | day | 0.18 | 816.00 | 146.88 |
| 0115 | CoolieLabour | day | 1.13 | 736.00 | 831.68 |
| 9999 | SundriesMaterial | L.S. | 22.36 | 2.27 | 50.76 |
- TOTAL
- 5,843.31
- Add 1 % Water charges on “W”
- 58.43
- TOTAL
- 5,901.74
- Add GST on “X” (multiplying factor 0.2127)
- 1,255.30
- TOTAL
- 7,157.04
- Add 15% CPOH on “Y”
- 1,073.56
- TOTAL
- 8,230.60
- Add Cess @ 1% on “Z”
- 82.31
- Cost of 1 Cum.
- 8,312.91
- Say
- 8,312.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 327. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.