Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level

Cement mortar 1:3 (1 cement :3 coarse sand)
Item number
6.13.1
Analysis basis
10 sqm
Priced inputs
8
Derived rate
₹1,150.50/ SQM
D-01/RATE ANALYSISITEM 6.13.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.13.1 (Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level Cement mortar 1:3 (1 cement :3 coarse sand)) is derived from 8 priced inputs for 10 sqm and works out to ₹1,150.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:3
  • Extra labour for lifting materials:
  • 10 x 0.115 x1.13
ANALYSIS OF RATES · ITEM 6.13.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2602MATCommon burnt clay F.P.S. (non modular) bricks class designation 7.51000 Nos0.5654,724.002,669.06
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum0.284,881.951,366.95
9999MATSundries & ScaffoldingL.S.13.522.2730.69
0123LABMason 1st classMason 1st classday0.6897.00538.20
0124LABMason 2nd classMason 2nd classday0.6816.00489.60
0115LABCoolieday2736.001,472.00
0101LABBhistiday0.7816.00571.20
0115LABCoolieday1.29736.00949.44
BUILD-UP TO RATE
TOTAL
8,087.14
Add 1 % Water charges on “W”
+80.87
TOTAL
8,168.01
Add GST on “X” (multiplying factor 0.2127)
+1,737.34
TOTAL
9,905.35
Add 15% CPOH on “Y”
+1,485.80
TOTAL
11,391.15
Add Cess @ 1% on “Z”
+113.91
Cost for 10 sqm.
11,505.06
Cost for 1 sqm.
1,150.51
SAY
₹1,150.50
D-02/SOURCEPRINTED PAGE 317
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
317

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 317. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.