Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundations and plinth in
- Item number
- 6.12.1
- Analysis basis
- 10 sqm
- Priced inputs
- 7
- Derived rate
- ₹931.75/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.12.1 (Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundations and plinth in : Cement mortar 1:3 (1 cement : 3 coarse sand)) is derived from 7 priced inputs for 10 sqm and works out to ₹931.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1:3
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2602 | MAT | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.565 | 4,724.00 | 2,669.06 |
| SUB | Cement mortar 1:3 (1 cement : 3 coarse sand) (Rate as per item No 3.8)Rate as per item 3.8 | cum | 0.28 | 4,881.95 | 1,366.95 | |
| 9999 | MAT | Sundries & Scaffolding | L.S. | 13.52 | 2.27 | 30.69 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.45 | 897.00 | 403.65 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.45 | 816.00 | 367.20 |
| 0115 | LAB | Coolie | day | 1.55 | 736.00 | 1,140.80 |
| 0101 | LAB | Bhisti | day | 0.7 | 816.00 | 571.20 |
- TOTAL
- 6,549.55
- Add 1 % Water charges on “W”
- +65.50
- TOTAL
- 6,615.05
- Add GST on “X” (multiplying factor 0.2127)
- +1,407.02
- TOTAL
- 8,022.07
- Add 15% CPOH on “Y”
- +1,203.31
- TOTAL
- 9,225.38
- Add Cess @ 1% on “Z”
- +92.25
- Cost for 10 sqm.
- 9,317.63
- Cost for 1 sqm.
- 931.76
- SAY
- ₹931.75
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 316
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 316. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.