40 mm thick marble chips flooring rubbed and polished to granolithic finish, under layer 34 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) and top layer 6mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from 1 mm to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume, including cement slurry etc. complete
- Item number
- 11.9.5
- Analysis basis
- 10 sqm
- Priced inputs
- 3
- Derived rate
- ₹1,061.70/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.9.5 (40 mm thick marble chips flooring rubbed and polished to granolithic finish, under layer 34 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) and top layer 6mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from 1 mm to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume, including cement slurry etc. complete : Light shade pigment with ordinary cement) is derived from 3 priced inputs for 10 sqm and works out to ₹1,061.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- shade pigment instead of dark shade
- pigment
- Add difference of cost due to using light
- Add for
- Deduct for
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 11.9.1 of SH: FlooringRate as per item 11.9.1 | sqm | 10 | 1,065.75 | 10,657.50 | |
| 0875 | MAT | Red, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigment | kilogram | 2.84 | 65.00 | 184.60 |
| 0874 | MAT | Black colour dark shade pigment | kilogram | -2.84 | 75.00 | -213.00 |
- TOTAL
- 10,629.10
- Add 1 % Water charges on “W-A”
- -0.28
- TOTAL
- 10,628.82
- Add GST on “X-A” (multiplying factor 0.2127)
- -6.10
- TOTAL
- 10,622.72
- Add 15% CPOH on “Y-A”
- -5.22
- TOTAL
- 10,617.50
- Add Cess @ 1% on “Z-A”
- -0.40
- Cost of 10 sqm
- 10,617.10
- cost of 1 sqm
- 1,061.71
- SAY
- ₹1,061.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 763
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 763. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.