Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar

Polished Granite stone slab of all colour and texture except Black, Cherry/Ruby Red

Item number
11.56.2
Analysis basis
Details of cost for 10.00 sqm
Priced inputs
11
Derived rate
3,071.05 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.56.2 Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar Polished Granite stone slab of all colour and texture except Black, Cherry/Ruby Red — is derived from 11 priced inputs for 10.00 sqm and works out to ₹3,071.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 18 mm thick polished finish granite stone
  • slab 10.00 sqm + 1.50 (Add for wastage
  • 15%)= 11.50 sqm
  • LABOUR :
CodeInputUnitQuantityRate (INR)Amount (INR)
729918 mm thick Polished finish granite stone slab of all colour and texture except Black, Cherry/Ruby Red (slab area more than 0.5 sqm)Granite stone slab all colour except black, cherry/ruby red 18 mm thick (slab area above 0.50 sqm)Materialsqm11.51,290.0014,835.00
Rate as per Item No.3.9 of SH: MORTARSRate as per item 3.9Sub-analysiscum0.2244,211.70943.42
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.055,156.00257.80
0874Black colour dark shade pigmentMaterialkilogram4.575.00337.50
9999Mortar for pointing in white cement (11.22)MaterialL.S.25.352.2757.54
0124Mason 2nd classMason 2nd classLabourday1.2816.00979.20
0114BeldarLabourday1736.00736.00
0115CoolieLabourday1736.00736.00
0139Skilled Beldar (for floor rubbing etc.)Labourday2816.001,632.00
0019Machine for cutting (hand grinding)Hand Grinder for mirror polishMachineryday2300.00600.00
9999SundriesMaterialL.S.208.132.27472.46
TOTAL
21,586.92
Add 1 % Water charges on “W”
215.87
TOTAL
21,802.79
Add GST on “X” (multiplying factor 0.2127)
4,637.45
TOTAL
26,440.24
Add 15% CPOH on “Y”
3,966.04
TOTAL
30,406.28
Add Cess @ 1% on “Z”
304.06
Cost of 10 sqm
30,710.34
Cost of 1 sqm
3,071.03
Say
3,071.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 847. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works