CPWD Analysis of Rates · Flooring
Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar
Polished Granite stone slab of all colour and texture except Black, Cherry/Ruby Red
- Item number
- 11.56.2
- Analysis basis
- Details of cost for 10.00 sqm
- Priced inputs
- 11
- Derived rate
- ₹3,071.05 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.56.2 — Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar Polished Granite stone slab of all colour and texture except Black, Cherry/Ruby Red — is derived from 11 priced inputs for 10.00 sqm and works out to ₹3,071.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 18 mm thick polished finish granite stone
- slab 10.00 sqm + 1.50 (Add for wastage
- 15%)= 11.50 sqm
- LABOUR :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7299 | 18 mm thick Polished finish granite stone slab of all colour and texture except Black, Cherry/Ruby Red (slab area more than 0.5 sqm)Granite stone slab all colour except black, cherry/ruby red 18 mm thick (slab area above 0.50 sqm)Material | sqm | 11.5 | 1,290.00 | 14,835.00 |
| Rate as per Item No.3.9 of SH: MORTARSRate as per item 3.9Sub-analysis | cum | 0.224 | 4,211.70 | 943.42 | |
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 0.05 | 5,156.00 | 257.80 |
| 0874 | Black colour dark shade pigmentMaterial | kilogram | 4.5 | 75.00 | 337.50 |
| 9999 | Mortar for pointing in white cement (11.22)Material | L.S. | 25.35 | 2.27 | 57.54 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 1.2 | 816.00 | 979.20 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 0115 | CoolieLabour | day | 1 | 736.00 | 736.00 |
| 0139 | Skilled Beldar (for floor rubbing etc.)Labour | day | 2 | 816.00 | 1,632.00 |
| 0019 | Machine for cutting (hand grinding)Hand Grinder for mirror polishMachinery | day | 2 | 300.00 | 600.00 |
| 9999 | SundriesMaterial | L.S. | 208.13 | 2.27 | 472.46 |
- TOTAL
- 21,586.92
- Add 1 % Water charges on “W”
- 215.87
- TOTAL
- 21,802.79
- Add GST on “X” (multiplying factor 0.2127)
- 4,637.45
- TOTAL
- 26,440.24
- Add 15% CPOH on “Y”
- 3,966.04
- TOTAL
- 30,406.28
- Add Cess @ 1% on “Z”
- 304.06
- Cost of 10 sqm
- 30,710.34
- Cost of 1 sqm
- 3,071.03
- Say
- 3,071.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 847. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.