Providing and laying flamed finish Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar
- Item number
- 11.55.1
- Analysis basis
- 10 sqm
- Priced inputs
- 10
- Derived rate
- ₹3,186.70/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.55.1 (Providing and laying flamed finish Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge : Flamed finish granite stone slab Jet Black, Cherry Red, Elite Brown, Cat Eye or equivalent) is derived from 10 priced inputs for 10 sqm and works out to ₹3,186.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 18mm thick - Flamed finish granite slab =
- 10.00 sqm+Add for wastage 15% =1.50
- sqm, Total 11.50 sqm
- LABOUR :
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1239 | MAT | 18 mm thick Flamed finish granite stone slab | sqm | 11.5 | 1,200.00 | 13,800.00 |
| SUB | Rate as per Item No.3.9 of SH: MORTARSRate as per item 3.9 | cum | 0.224 | 4,211.70 | 943.42 | |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.05 | 5,156.00 | 257.80 |
| 0874 | MAT | Black colour dark shade pigment | kilogram | 4.5 | 75.00 | 337.50 |
| 9999 | MAT | Mortar for pointing in white cement | L.S. | 25.35 | 2.27 | 57.54 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.2 | 816.00 | 979.20 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
| 0115 | LAB | Coolie | day | 1 | 736.00 | 736.00 |
| 0139 | LAB | Skilled Beldar (for floor rubbing etc.) | day | 5 | 816.00 | 4,080.00 |
| 9999 | MAT | Sundries | L.S. | 208.13 | 2.27 | 472.46 |
- TOTAL
- 22,399.92
- Add 1 % Water charges on “W”
- +224.00
- TOTAL
- 22,623.92
- Add GST on “X” (multiplying factor 0.2127)
- +4,812.11
- TOTAL
- 27,436.03
- Add 15% CPOH on “Y”
- +4,115.40
- TOTAL
- 31,551.43
- Add Cess @ 1% on “Z”
- +315.51
- Cost of 10 sqm
- 31,866.94
- Cost of 1 sqm
- 3,186.69
- SAY
- ₹3,186.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 846
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 846. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.