Providing and laying Vitrified tiles in floor with different sizes (thickness to be specified by the manufacturer), with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid with cement based high polymer modified quick set tile adhesive (water based) conforming to IS : 15477, in average 6 mm thickness, including grouting of joints (Payment for grouting of joints to be made separately)
- Item number
- 11.49.3
- Analysis basis
- 1 sqm
- Priced inputs
- 6
- Derived rate
- ₹2,060.75/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.49.3 (Providing and laying Vitrified tiles in floor with different sizes (thickness to be specified by the manufacturer), with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid with cement based high polymer modified quick set tile adhesive (water based) conforming to IS : 15477, in average 6 mm thickness, including grouting of joints (Payment for grouting of joints to be made separately) Size of Tile 800x800 mm) is derived from 6 priced inputs for 1 sqm and works out to ₹2,060.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Vitrified floor tiles 80 x 80 cm size = 1.00
- sqm+
- 0.025 sqm
- Total = 1.025 sqm
- Add wastage & breakage @ 2.5% =
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8622 | MAT | Vitrified floor tile 80x80 cmVitrified floor tile 80x80 cm conforming to IS 15622:2006 group (B1a) | sqm | 1.025 | 780.00 | 799.50 |
| 9977 | MAT | Carriage of tiles | L.S. | 6.24 | 2.27 | 14.16 |
| 8731 | MAT | High polymer modified quickset tile adhesive | per kg | 10 | 10.00 | 100.00 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.2 | 897.00 | 179.40 |
| 0115 | LAB | Coolie | day | 0.4 | 736.00 | 294.40 |
| 9988 | MAT | Sundries including carriage of quick set polymer etc | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 1,448.55
- Add 1 % Water charges on “W”
- +14.49
- TOTAL
- 1,463.04
- Add GST on “X” (multiplying factor 0.2127)
- +311.19
- TOTAL
- 1,774.23
- Add 15% CPOH on “Y”
- +266.13
- TOTAL
- 2,040.36
- Add Cess @ 1% on “Z”
- +20.40
- Cost for 1 sqm
- 2,060.76
- SAY
- ₹2,060.75
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 838
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 838. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.