Skip to main content
R/DAR 2023

Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70 kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-incharge

Size of Tile 1000x1000 mm
Item number
11.48.4
Analysis basis
1 sqm
Priced inputs
4
Derived rate
₹174.50/ SQM
D-01/RATE ANALYSISITEM 11.48.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.48.4 (Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70 kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-incharge Size of Tile 1000x1000 mm) is derived from 4 priced inputs for 1 sqm and works out to ₹174.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 11.48.4DETAILS OF COST FOR 1 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8682MATEpoxy GroutKg0.11418.0045.98
0123LABMason 1st classMason 1st classday0.04897.0035.88
0115LABCoolieday0.04736.0029.44
9988MATSundries including carriageL.S.52.2711.35
BUILD-UP TO RATE
TOTAL
122.65
Add 1 % Water charges on “W”
+1.23
TOTAL
123.88
Add GST on “X” (multiplying factor 0.2127)
+26.35
TOTAL
150.23
Add 15% CPOH on “Y”
+22.53
TOTAL
172.76
Add Cess @ 1% on “Z”
+1.73
Cost for 1 sqm
174.49
SAY
₹174.50
D-02/SOURCEPRINTED PAGE 837
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
837

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 837. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.