CPWD Analysis of Rates · Flooring
Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70 kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-incharge
Size of Tile 1000x1000 mm
- Item number
- 11.48.4
- Analysis basis
- Details of cost for 1 sqm
- Priced inputs
- 4
- Derived rate
- ₹174.50 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.48.4 — Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70 kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-incharge Size of Tile 1000x1000 mm — is derived from 4 priced inputs for 1 sqm and works out to ₹174.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8682 | Epoxy GroutMaterial | Kg | 0.11 | 418.00 | 45.98 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.04 | 897.00 | 35.88 |
| 0115 | CoolieLabour | day | 0.04 | 736.00 | 29.44 |
| 9988 | Sundries including carriageMaterial | L.S. | 5 | 2.27 | 11.35 |
- TOTAL
- 122.65
- Add 1 % Water charges on “W”
- 1.23
- TOTAL
- 123.88
- Add GST on “X” (multiplying factor 0.2127)
- 26.35
- TOTAL
- 150.23
- Add 15% CPOH on “Y”
- 22.53
- TOTAL
- 172.76
- Add Cess @ 1% on “Z”
- 1.73
- Cost for 1 sqm
- 174.49
- Say
- 174.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 837. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.