Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70 kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-incharge

Size of Tile 600x600 mm
Item number
11.48.2
Analysis basis
1 sqm
Priced inputs
4
Derived rate
₹309.05/ SQM
D-01/RATE ANALYSISITEM 11.48.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.48.2 (Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70 kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-incharge Size of Tile 600x600 mm) is derived from 4 priced inputs for 1 sqm and works out to ₹309.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 11.48.2DETAILS OF COST FOR 1 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8682MATEpoxy GroutKg0.18418.0075.24
0123LABMason 1st classMason 1st classday0.08897.0071.76
0115LABCoolieday0.08736.0058.88
9988MATSundries including carriageL.S.52.2711.35
BUILD-UP TO RATE
TOTAL
217.23
Add 1 % Water charges on “W”
+2.17
TOTAL
219.40
Add GST on “X” (multiplying factor 0.2127)
+46.67
TOTAL
266.07
Add 15% CPOH on “Y”
+39.91
TOTAL
305.98
Add Cess @ 1% on “Z”
+3.06
Cost for 1 sqm
309.04
SAY
₹309.05
D-02/SOURCEPRINTED PAGE 836
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
836

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 836. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.