Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70 kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-incharge
- Item number
- 11.48.2
- Analysis basis
- 1 sqm
- Priced inputs
- 4
- Derived rate
- ₹309.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.48.2 (Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70 kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-incharge Size of Tile 600x600 mm) is derived from 4 priced inputs for 1 sqm and works out to ₹309.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8682 | MAT | Epoxy Grout | Kg | 0.18 | 418.00 | 75.24 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.08 | 897.00 | 71.76 |
| 0115 | LAB | Coolie | day | 0.08 | 736.00 | 58.88 |
| 9988 | MAT | Sundries including carriage | L.S. | 5 | 2.27 | 11.35 |
- TOTAL
- 217.23
- Add 1 % Water charges on “W”
- +2.17
- TOTAL
- 219.40
- Add GST on “X” (multiplying factor 0.2127)
- +46.67
- TOTAL
- 266.07
- Add 15% CPOH on “Y”
- +39.91
- TOTAL
- 305.98
- Add Cess @ 1% on “Z”
- +3.06
- Cost for 1 sqm
- 309.04
- SAY
- ₹309.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 836
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 836. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.